Coal progressive rehabilitation and closure plan

PRCP-EPML00841513 · QUEENSLAND POWER (AUSTRALIA) PTY LTD

PRC plan PRCP-EPML00841513-V1 for QUEENSLAND POWER (AUSTRALIA) PTY LTD (EPML00841513), coal. Current schedule final milestone 2042-12-10; 8 rehabilitation and improvement areas.

Environmental authority
EPML00841513
Holders
QUEENSLAND POWER (AUSTRALIA) PTY LTD; MILLMERRAN INVESTMENT COMPANY I PTY LTD; MILLMERRAN INVESTMENT COMPANY II PTY LTD; Millmerran Investment Company III Pte Ltd; MILLMERRAN INVESTMENT COMPANY IV PTY LTD; Millmerran Investment Company V Pte Ltd; Millmerran Investment Company VI Pte Ltd; Queensland Power Company Limited
Tenures
ML50151
Plan versions
PRCP-EPML00841513-V1 (effective 2022-09-30)
Current schedule final milestone
2042-12-10
Areas in current schedule
8 · 1,976 ha

Schedule versions

VersionEffectiveFinal milestoneAreasDocument
1 (current)2022-09-302042-12-108Schedule PDF

Rehabilitation and improvement areas

From the current schedule's tables. Land use categories are keyword groupings; the schedule's wording is shown beneath.

AreaActivitiesHectaresPost-mining land useFirst milestonePage
RA1rehabilitationWestern Mining Area (A Pit / B Pit / C Pit / G Pit, Waste Rock Dump, Ash Burial)725.7GrazingGrazing10 December 202222
RA2rehabilitationEastern Mining Area (AN Pit, E Pit, F Pit, CK Pit, H Pit, I Pit and J Pit, Waste Rock Dump and Ash Burial, part of decommissioned H Pit Flood Levee, Southern Flood Levee)868.5GrazingGrazing10 December 202223
RA3rehabilitationROM hill / Magazine Area26.9GrazingGrazing10 December 202224
RA4rehabilitationBack Creek Diversion (including decommissioned Northern Flood levee, decommissioned H Pit Flood Levee, A Pit, H Pit)225.4Native ecosystemNative Ecosystem10 December 202225
RA5rehabilitationWaste Rock Dump28.2GrazingGrazing - Wildlife corridors10 December 202226
RA6rehabilitationRoads42.9Infrastructure, industrial or residentialRoads10 December 202227
RA7rehabilitationWater Storage (North Dam, F1 & F2 Dam, Swan Lake, Pit E Dam, SED Dam 1, SED Dam 2)53.8GrazingWater Storage (Grazing)01 September 203428
RA8rehabilitationWorkshop shed, administration building, undercover parking area, wash down facility, fire systems, water tanks and fencing5.1Infrastructure, industrial or residentialPermanent Infrastructure01 September 203229