Coal progressive rehabilitation and closure plan

PRCP-EPML00657913 · CONSTELLATION MINING PTY LTD

PRC plan PRCP-EPML00657913-V1 for CONSTELLATION MINING PTY LTD (EPML00657913), coal. Current schedule final milestone 2063-12-10; 6 rehabilitation and improvement areas.

Environmental authority
EPML00657913
Holders
CONSTELLATION MINING PTY LTD
Tenures
ML80173
Plan versions
PRCP-EPML00657913-V1 (effective 2023-05-03)
Current schedule final milestone
2063-12-10
Areas in current schedule
6 · 601 ha

Schedule versions

VersionEffectiveFinal milestoneAreasDocument
1 (current)2023-05-032063-12-106Schedule PDF

Rehabilitation and improvement areas

From the current schedule's tables. Land use categories are keyword groupings; the schedule's wording is shown beneath.

AreaActivitiesHectaresPost-mining land useFirst milestonePage
RA1rehabilitationBuilt Infrastructure205.0GrazingGrazing Pasture10/12/20549
RA2rehabilitationCodisposal Area (CDA)104.0GrazingGrazing Pasture10/12/203710
RA3rehabilitationAt-Grade Disturbance102.2GrazingGrazing Pasture11/12/205711
RA4rehabilitationExploration Activities50.0GrazingGrazing Pasture10/12/202312
RA5rehabilitationUnderground Mining Surface Facilities140.2GrazingGrazing Pasture10/12/205413
RA6rehabilitationLongwall Mining Subsidence Areas1424.1 (Full extent of longwall subsidence area)GrazingGrazing Pasture11/12/203814