Minerals environmental authority

EPML00658113 · CEMENT AUSTRALIA (EXPLORATION) PTY LTD

Minerals environmental authority EPML00658113 (CEMENT AUSTRALIA (EXPLORATION) PTY LTD), Granted. 107 conditions indexed. No PRC plan.

Status
Granted
Holders
CEMENT AUSTRALIA (EXPLORATION) PTY LTD; CEMENT AUSTRALIA (QUEENSLAND) PTY LIMITED
Tenures
ML3629; ML3630; ML3631; ML3632; ML3659; ML7629; ML80002; ML80127; ML80156
PRC plan
None
How it was read
Numbered conditions, partial, plus page text
Register
Register record · Instrument PDF

Conditions

107 numbered conditions read from the current instrument. Page numbers link into the register PDF.

  1. A1

    This environmental authority authorises environmental harm referred to in the conditions. Where there is no condition or this environmental authority is silent on a matter, the lack of a condition or silence does not authorise environmental harm.

  2. A2

    In carrying out the mining activity authorised by this environmental authority, the environmental authority holder must comply with the authorised disturbance areas listed in Table A1 - Authorised disturbance and as depicted in Figure 1 - Project Infrastructure Layout Mine Area and Support Infrastructure. Table A1 - Authorised disturbance Mine Feature Name Location[1] (GDA2020, Maximum Description / Purpose decimal degrees[2]) Disturbance Water Storage / Includes: water storages, Settling Ponds Latitude Longitude Area (ha) sediment settling ponds. Void / Mine Workings / Haul -23.87743 150.96314 11 Voids, haul roads, mine Roads workings, access roads -23.87779 150.95840 209 Includes: overburden and spoil dumps Spoil Dumps -23.88061 150.95264 53 Includes: Stockpiles, Crushing Plant, Offices, Workshops, Rail Stockpiling/Crushing/Loading -23.87646 150.95848 37 Loop and Infrastructure -23.87406 150.96226 -23.87551 150.96747 [1] Coordinates indicate location of mine feature not boundaries. [2] Decimal degrees to be provided to a minimum of 5 decimal places.

    page 5Land and soil
  3. A3

    The environmental authority holder must: a) Install all measures, plant and equipment necessary to ensure compliance with the conditions of this environmental authority; and b) Maintain such measures, plant and equipment in a proper and efficient manner; and c) Operate such measures, plant and equipment in a proper and efficient manner; and, d) Ensure all instruments and devices used for the measurement or monitoring of any parameter under any condition of this environmental authority are properly calibrated.

    page 5Monitoring and reporting
  4. A4

    All flammable, corrosive and combustible liquids, including petroleum products, must be stored and handled in accordance with: a) The latest edition of AS1940--The storage and handling of flammable and combustible liquids where applicable; b) The current Australian Standard where applicable; or c) Where no relevant Australian Standard exists, store such materials within an on-site containment system sufficient to prevent release to the receiving environment. OFFICIAL Permit Environmental authority EPML00658113

  5. A5

    Financial assurance must be lodged in the amount, the form, and within the time required by the administering authority.

  6. A6

    Any records kept or created in relation to this environmental authority must be: a) kept for a period of at least five years; and b) provided to the administering authority on request; and c) provided to the administering authority in the format requested.

    page 6Monitoring and reporting
  7. A7

    An appropriately qualified person(s) must monitor and record all indicator(s) required by and in accordance with this environmental authority.

    page 6Monitoring and reporting
  8. A8

    When required by the administering authority, monitoring must be undertaken in the manner prescribed by the administering authority to investigate a complaint arising from the activity. The monitoring results must be recorded.

    page 6Monitoring and reporting
  9. A9

    The following must be recorded in relation to all monitoring required under a condition of this environmental authority: a) The date and time when the sample was taken; b) The location where the sample was taken; c) The results of all monitoring and details of exceedances of the conditions of this environmental authority; and d) Any other pertinent details of relevance to interpreting the sample results (i.e. stream or release flow rate, wind, conditions, atmospheric conditions, any relevant observations such as odour or colouration).

    page 6Air, Monitoring and reporting
  10. A10

    The environmental authority holder must implement and maintain a risk management system for mining activities which mirrors the content requirement of the Standard for Risk Management (ISO31000:2009), or the Standard for Environmental Management Systems (ISO14001), or the latest edition of an Australia standard for risk management, to the extent relevant to environmental management.

  11. A11

    The environmental authority holder must notify the administering authority within twenty four (24) hours of becoming aware of any incident or event which does or may contravene a condition of this environmental authority. Notification to the administering authority must be provided to the administering authority Pollution Hotline on 1300 130 372 and PollutionHotline@ehp.qld.gov.au.

    page 6Monitoring and reporting
  12. A12

    Within ten (10) business days following the initial notification of an incident or event, or receipt of monitoring results, whichever is the latter, further written advice must be provided to the administering authority, including the following: a) Results and interpretation of any samples taken and analysed; and b) Outcomes of actions taken at the time to prevent or minimise unlawful environmental harm; and c) Proposed actions to prevent recurrence of the emergency or incident. OFFICIAL Permit Environmental authority EPML00658113

    page 6Monitoring and reporting
  13. A13

    The environmental authority holder must record all environmental complaints received about the mining activities including: a) Name, address and contact number of the complainant; b) Time and date of complaint; c) Reasons for the complaint; d) Investigations undertaken; e) Conclusions formed; f) Actions taken to resolve the complaint; g) Any abatement measures implemented; and h) Person responsible for resolving the complaint.

    page 7Monitoring and reporting
  14. A14

    Compliance with the conditions of this environmental authority must be audited at regular intervals not exceeding once every three (3) years. The audit must be conducted by a suitably qualified third party auditor. The environmental authority holder must submit a final version of the auditor's report to the administering authority within ninety (90) days of completing the audit.

    page 7Monitoring and reporting
  15. A15

    All waste generated as part of the mining activities must be lawfully reused, recycled, or removed to an off-site facility that can lawfully accept the waste.

    page 7Waste
  16. A16

    Scrap tyres stored awaiting disposal or transport for take-back and recycling, or waste to energy options must be stored in stable stacks and at least 10 metres away from any other scrap tyre storage area, or combustible or flammable material, including vegetation.

    page 7Waste, Biodiversity
  17. A17

    All reasonable and practicable fire prevention measures must be implemented, including removal of grass and other materials within a 10 metre radius of the scrap tyre storage area.

  18. A18

    Where no feasible recycling or waste-to-energy options are available, disposing of scrap tyres resulting from the mining activities in spoil emplacements is acceptable, provided tyres are placed as deep in the spoil as reasonably practicable.

    page 7Waste
  19. A19

    Scrap tyres resulting from the mining activities disposed within the operational land must not impede saturated aquifers or compromise the stability of the consolidated landform.

    page 7Groundwater
  20. A20

    The consequence category of any structure must be assessed by a suitably qualified and experienced person in accordance with the Manual for Assessing Consequence Categories and Hydraulic Performance of Dams (EM635) at the following times: a) Prior to the design and construction of the structure, if it is not an existing structure; or b) Prior to any change in its purpose or the nature of its stored contents.

    page 7Regulated structures
  21. A21

    A consequence assessment report and certification must be prepared for each structure assessed and the report may include a consequence assessment for more than one structure.

    page 7Monitoring and reporting
  22. A22

    Certification must be provided by the suitably qualified and experienced person who undertook the assessment, in the form set out in the Manual for Assessing Consequence Categories and Hydraulic OFFICIAL Permit Environmental authority EPML00658113

    page 7Regulated structures
  23. A23

    Except for an existing structure, all regulated structures must be designed by, and constructed under the supervision of, a suitably qualified and experienced person in accordance with the requirements of the

    page 8Regulated structures
  24. A24

    Except for an existing structure, construction of a regulated structure is prohibited unless a) The environmental authority holder has submitted a consequence category assessment report and certification to the administering authority; b) Certification for the design, design plan and the associated operating procedures has been certified by a suitably qualified and experienced person in compliance with the relevant condition of this environmental authority.

    page 8Regulated structures, Monitoring and reporting
  25. A25

    Except for an existing structure, certification must be provided by the suitably qualified and experienced person who oversees the preparation of the design plan in the form set out in the Manual for be recorded in the Register of Regulated Structures.

    page 8Regulated structures
  26. A26

    Except for an existing structure, regulated structures must: a) Be designed and constructed in compliance with the Manual for Assessing b) Be designed and constructed with due consideration given to ensuring that the design integrity would not be compromised on account of: i. floodwaters from entering the regulated dam from any watercourse or drainage line; ii. wall failure due to erosion by floodwaters arising from any watercourse or drainage line. c) Have the floor and sides of the dam designed and constructed to prevent or minimise the passage of the wetting front and any entrained contaminants through either the floor or sides of the dam during the operational life of the dam and for any period of decommissioning and rehabilitation of the dam.

    page 8Rehabilitation, Surface water, Regulated structures, Land and soil
  27. A27

    Except for an existing structure, certification by the suitably qualified and experienced person who supervises the construction must be submitted to the administering authority on the completion of construction of the regulated structure, and state that: a) The `as constructed' drawings and specifications meet the original intent of the design plan for that regulated structure; b) Construction of the regulated structure is in accordance with the design plan.

    page 8Regulated structures
  28. A28

    All affected persons must be provided with a copy of the emergency action plan in place for each regulated structure: a) For existing structures that are regulated structures, within ten (10) business days of this condition taking effect; b) Prior to the operation of the new regulated structure; and c) If the emergency action plan is amended, within five (5) business days of it being amended. OFFICIAL Permit Environmental authority EPML00658113

    page 8Regulated structures
  29. A29

    Operation of a regulated structure, except for an existing structure, is prohibited unless the environmental authority holder has submitted to the administering authority a) One (1) paper copy and one electronic copy of the design plan and certification of the `design plan' in accordance with condition A24; b) A set of `as constructed' drawings and specifications; c) Certification of those `as constructed drawings and specifications' in accordance with condition A27; d) Where the regulated structure is to be managed as part of an integrated containment system for the purpose of sharing the design storage allowance (DSA) volume across the system, a copy of the certified system design plan; e) The requirements of this authority relating to the construction of the regulated structure have been met; f) The holder has entered the details required under this authority, into a Register of Regulated Structures; and g) There is a current operational plan for the regulated structure.

    page 9Regulated structures
  30. A30

    Each regulated structure must be maintained and operated, for the duration of its operational life until decommissioned and rehabilitated, in a manner that is consistent with the current operational plan and, if applicable, the current design plan and associated certified `as constructed' drawings.

    page 9Rehabilitation, Regulated structures
  31. A31

    For regulated structures that have not been certified as low consequence category for `failure to contain - overtopping', the mandatory reporting level (MRL) must be marked on a regulated dam in such a way that during routine inspections of that dam, it is clearly observable.

    page 9Regulated structures, Monitoring and reporting
  32. A32

    For regulated structures that have not been certified as low consequence category for `failure to contain - overtopping', the environmental authority holder must, as soon as practical but within forty-eight (48) hours of becoming aware, notify the administering authority when the level of the contents of a regulated dam reaches the MRL.

    page 9Regulated structures, Monitoring and reporting
  33. A33

    For regulated structures that have not been certified as low consequence category for `failure to contain - overtopping', the environmental authority holder must, immediately on becoming aware that the MRL has been reached, act to prevent the occurrence of any unauthorised discharge from the regulated dam.

    page 9Regulated structures
  34. A34

    For regulated structures that have not been certified as low consequence category for `failure to contain - overtopping', the environmental authority holder must record any changes to the MRL in the Register of Regulated Structures.

    page 9Regulated structures, Monitoring and reporting
  35. A35

    The environmental authority holder must assess the performance of each regulated dam or linked containment system over the preceding November to May period based on actual observations of the available storage in each regulated dam or linked containment system taken prior to 1 July of each year.

    page 9Regulated structures
  36. A36

    By 1 November of each year, storage capacity must be available in each regulated dam (or network of linked containment systems with a shared DSA volume), to meet the DSA volume for the dam (or network of linked containment systems). OFFICIAL Permit Environmental authority EPML00658113

    page 9Regulated structures
  37. A37

    The environmental authority holder must, as soon as possible but within forty-eight (48) hours of becoming aware that the regulated dam (or network of linked containment systems) will not have the available storage to meet the DSA volume on 1 November of any year, notify the administering authority.

    page 10Regulated structures, Monitoring and reporting
  38. A38

    The environmental authority holder must, immediately on becoming aware that a regulated dam (or network of linked containment systems) will not have the available storage to meet the DSA volume on 1 November of any year, act to prevent the occurrence of any unauthorised discharge from the regulated dam or linked containment systems.

    page 10Regulated structures
  39. A39

    Each regulated structure must be inspected each calendar year by a suitably qualified and experienced person.

    page 10Regulated structures
  40. A40

    At each annual inspection, the condition and adequacy of all components of the regulated structure must be assessed and a suitably qualified and experienced person must prepare an annual inspection report containing details of the assessment and include a recommendations section, with any recommended actions to ensure the integrity of the regulated structure or a positive statement that no recommendations are required.

    page 10Regulated structures, Monitoring and reporting
  41. A41

    The suitably qualified and experienced person who prepared the annual inspection report must certify the report in accordance with the Manual for Assessing Consequence Categories and Hydraulic

    page 10Regulated structures, Monitoring and reporting
  42. A42

    The environmental authority holder must within twenty (20) business days of receipt of the annual inspection report, provide to the administering authority: a) The recommendations section of the annual inspection report; b) If applicable, any actions being taken in response to those recommendations; and c) If, following receipt of the recommendations and (if applicable) recommended actions, the administering authority requests a copy of the annual inspection report from the environmental authority holder, provide this to the administering authority within ten (10) business days of receipt of the request.

    page 10Monitoring and reporting
  43. A43

    The environmental authority holder must provide a copy of any reports, documentation and certifications prepared under this authority, including but not limited to any Register of Regulated Structures, consequence assessment, design plan and other supporting documentation, to a new environmental authority holder on transfer of this activity. OFFICIAL Permit Environmental authority EPML00658113

    page 10Regulated structures, Monitoring and reporting
  44. A44

    Regulated structures must not be abandoned but be either: a) Decommissioned and rehabilitated to achieve compliance with Schedule E of this environmental authority; or b) Be left in-situ for a use by the landholder provided that: i. it no longer contains contaminants that will migrate into the environment; ii. it contains water of a quality that is demonstrated to be suitable for its intended use(s); and iii. the environmental authority holder and the landholder agree in writing that the: 1. dam will be used by the landholder following the cessation of the environmentally relevant activity(ies); and 2. landholder is responsible for the dam, on and from an agreed date.

    page 11Rehabilitation, Regulated structures
  45. A45

    A Register of Regulated Structures must be established and maintained by the environmental authority holder for each regulated structure.

    page 11Regulated structures
  46. A46

    The environmental authority holder must provisionally enter the required information in the Register of Regulated Structures when a design plan for a regulated structure is submitted to the administering authority.

    page 11Regulated structures
  47. A47

    The environmental authority holder must make a final entry of the required information in the Register of Regulated Structures once compliance with condition A29 has been achieved.

    page 11Regulated structures
  48. A48

    The environmental authority holder must ensure that the information contained in the Register of Regulated Structures is current and complete on any given day.

    page 11Regulated structures
  49. A49

    All entries in the Register of Regulated Structures must be approved by the chief executive officer for the environmental authority holder, or their delegate, as being accurate and correct.

    page 11Regulated structures
  50. A50

    The environmental authority holder must, at the same time as providing the annual return, supply to the administering authority a copy of the records contained in the Register of Regulated Structures, in the electronic format required by the administering authority. END OF CONDITIONS FOR SCHEDULE A OFFICIAL Permit Environmental authority EPML00658113 Schedule B - Air

    page 11Regulated structures, Monitoring and reporting
  51. B1

    The release of dust or particulate matter, or both, resulting from the mining activity must not cause environmental harm to an environmental value for air.

  52. B2

    When measured at any area or place outside of the mining lease boundary, airborne contaminants generated by the mining activities must not cause the following levels to be exceeded: a) Dust deposition of 120 milligrams per square metre per day, averaged over 1 month, when monitored in accordance with the most recent version of Australian Standard AS3580.10.1 Methods for sampling and analysis of ambient air - Determination of particulate matter - Deposited matter - Gravimetric method. b) A concentration of particulate matter with an aerodynamic diameter of less than 10 micrometres (PM10) suspended in the atmosphere of 50 micrograms per cubic metre over a 24-hour averaging time, for no more than five exceedances recorded each year, when monitored in accordance with the most recent version of either: i. Australian Standard AS3580.9.6 Methods for sampling and analysis of ambient air - Determination of suspended particulate matter - PM10 high volume sampler with size-selective inlet - Gravimetric method, or ii. Australian Standard AS3580.9.9 Methods for sampling and analysis of ambient air - Determination of particulate matter - PM10 low volume sampler - Gravimetric method. END OF CONDITIONS FOR SCHEDULE B OFFICIAL Permit Environmental authority EPML00658113 Schedule C - Acoustic

    page 12Air, Monitoring and reporting
  53. C1

    Noise generated by the mining activities must not exceed the specified levels in Table C1 - Noise limits when measured at any sensitive receptor. Table C1 - Noise limits Location Noise Monday to Saturday Sundays and Public Holidays level 7am to 6pm to 10pm to 9am to 6pm to 10pm to dB(A) 6pm 10pm 7am 6pm 10pm 9am measured as: Dwelling LAeq, Bkg + Bkg + Bkg + Bkg + Bkg + Bkg + adj, 1 5dBA 3dBA 3dBA 5dBA 3dBA 3dBA hMoauxr Bkg + Bkg + Bkg + Bkg + Bkg + Bkg + LpA, 1 5dBA hNoouisr e 10dBA 5dBA 10dBA 5dBA 5dBA Commercial Monday to Saturday Sundays and Public Holidays level 7am to 6pm to 10pm to 7am to 6pm to 10pm to dB(A) 6pm 10pm 7am 6pm 10pm 7am measured as: LAeq, Bkg + Bkg + Bkg + Bkg + Bkg + Bkg + adj, 1 10dBA 5dBA 5dBA 10dBA 5dBA 5dBA hMoauxr Bkg + Bkg + Bkg + Bkg + Bkg + Bkg + LpA, 1 15dBA 10dBA 10dBA 15dBA 10dBA 10dBA A - A weightehdour Bkg = Background dB - Decibel LAeq - the A-weighted equivalent continuous Lp of the sample time T Lp - Sound pressure level Associated requirements:

    page 13Noise and vibration
  54. C2

    The environmental authority holder must ensure that blasting does not cause the limits for peak particle velocity and air blast overpressure in Table C2 - Blasting noise limits to be exceeded when measured at any sensitive receptor. OFFICIAL Permit Environmental authority EPML00658113 Table C2 - Blasting noise limits Blasting noise limits Sensitive receptor blasting noise limits Airblast overpressure 8am to 5pm Monday to Saturday Other times and Ground vibration peak Public holidays particle velocity 115dB (Linear) Peak for 9 out of 10 consecutive blasts No blasting initiated and not greater than 120dB (Linear) Peak at any time 5mm/second peak particle velocity for 9 out of 10 No blasting consecutive blasts and not greater than 10 mm/second peak particle velocity at any time

    page 13Noise and vibration
  55. C3

    When requested by the administering authority, noise monitoring and recording must include the following descriptor characteristics and matters: a) LAN,T (where N equals the statistical levels of 1, 10 and 90 and T = 15 mins); b) Background noise LA90; c) The level and frequency of occurrence of impulsive or tonal noise and any adjustment and penalties to statistical levels; d) Atmospheric conditions including temperature, relative humidity and wind speed and directions; e) Effects due to any extraneous factors such as traffic noise; f) Location, date and time of monitoring; g) If the complaint concerns low frequency noise, Max Lp(lin)T and one third octave band measurements in dB(lin) for centre frequencies in the 10-200 Hertz range. END OF CONDITIONS FOR SCHEDULE C OFFICIAL Permit Environmental authority EPML00658113 Schedule D - Water

    page 14Noise and vibration, Monitoring and reporting
  56. D1

    Contaminants that will, or have the potential to cause environmental harm must not be released directly or indirectly to any waters as a result of the authorised mining activities, except as permitted under the conditions of this environmental authority.

  57. D2

    The release of contaminants to waters must only occur from the release points specified in Table D1 - Contaminated water release points, sources and receiving waters. Table D1- Contaminated water release points, sources and receiving waters Release Location (GDA94) Water source[1] Receiving waters point[1] description Latitude Longitude (RP) East End Creek A -23.878593 150.967531 East End mining operations discharging East End Creek at Weir 1. 1 -23.878231 150.963540 East End mining operations discharging at Weir 6. [1] Locations depicted in Figure 2 - Release point and surface water monitoring locations.

    page 15Surface water, Monitoring and reporting
  58. D3

    The release of contaminants to waters in accordance with condition D2 must be monitored: a) at the release points specified in Table D1 - Contaminated water release points, sources and receiving waters as depicted in Figure 2 - Release points and surface water monitoring locations; and b) at the monitoring frequencies specified in Table D2 - Contaminant release limits; and c) for the quality characteristics identified in Table D2 - Contaminant release limits.

    page 15Surface water, Monitoring and reporting
  59. D4

    The release of contaminants to waters in accordance with condition D2 must not exceed the release limits stated in Table D2 - Contaminant release limits when measured at the release points specified in Table D1 - Contaminated water release points, sources and receiving waters for each quality characteristic. Table D2 - Contaminant release limits Quality characteristic Release limit [2] Monitoring frequency Electrical Conductivity 5,000 Daily during a release greater than 6 mega litres (micro siemens per per day. centimetre, -s/cm) Monthly for all other releases. pH (pH units) 6.5 (minimum) Turbidity (NTU) 8.5 (maximum) 20[1] [1] If turbidity at [the upstream monitoring point (Monitoring Point C)] is greater than Release Point A then no exceedance is to be recorded. [2] Release limits apply at Release Point 1 from 02 September 2022.

    page 15Surface water, Monitoring and reporting
  60. D5

    The release of contaminants to waters in accordance with condition D2 must only take place during periods of natural flow in the Larcom Creek.

  61. D6

    Releases to waters must be undertaken so as to not cause erosion of the bed and banks of the receiving waters, or cause a material build-up of sediment in such waters. OFFICIAL Permit Environmental authority EPML00658113

    page 15Surface water, Land and soil
  62. D7

    The rate and daily quantity of water released from the release points specified in Table D1 - Contaminated water release points, sources and receiving waters must be measured and recorded.

    page 16Surface water
  63. D8

    The environmental authority holder must determine and record stream flows in the receiving environment at the upstream reference monitoring point specified in Table D3 - Receiving waters monitoring sites.

    page 16Surface water, Monitoring and reporting
  64. D9

    If the release limits specified in Table D2 - Contaminant Release limits are exceeded, the holder of the environmental authority must notify the administering authority within twenty four (24) hours of receiving the results.

    page 16Monitoring and reporting
  65. D10

    The environmental authority holder must, within twenty eight (28) days of a release that is not compliant with the conditions of this environmental authority, provide a report to the administering authority detailing: a) the reason for the release; and b) the location of the release; and c) the total volume of the release and which (if any) part of this volume was non-compliant; and d) the total duration of the release and which (if any) part of this period was non-compliant; and e) all water quality monitoring results (including all laboratory analyses); and f) identification of any environmental harm as a result of the non-compliance; and g) all calculations; and h) any other matters pertinent to the water release event.

    page 16Monitoring and reporting
  66. D11

    The quality of the receiving waters must be monitored at the locations and frequency specified in Table

    page 16Surface water, Monitoring and reporting
  67. D3

    - Receiving waters monitoring sites as depicted in Figure 2 - Release points and surface water monitoring locations for each quality characteristic stated in Table D4 - Water quality objectives for receiving waters. OFFICIAL Permit Environmental authority EPML00658113 Table D3 - Receiving waters monitoring sites Monitoring point[1] Receiving waters location Location (GDA94) Monitoring frequency Latitude Longitude description Upstream reference monitoring point[1] Monitoring Point G Larcom Creek upstream of East TBD TBD Weekly -23.887238 150.977206 Weekly End Creek and Larcom Creek junction [2] Monitoring Point C Larcom Creek upstream of East End Creek and Larcom Creek junction (Location 5) Downstream monitoring points Monitoring Point D Larcom Creek downstream of -23.899252 150.976561 Weekly East End Creek and Larcom Creek Junction (at Weir 7) [1] Locations depicted in Figure 2 - Release point and surface water monitoring locations. [2] Upstream location must be outside of any influence from the releases from RP A TBD To be determined and provided to the administering authority by 02 December 2021.

    page 16Surface water, Monitoring and reporting
  68. D12

    Receiving waters measured from Monitoring Point D specified in Table D3 - Receiving waters monitoring sites must not exceed the corresponding Limit A specified in Table D4 - Water quality objectives for receiving waters on any five consecutive sampling occasions.

    page 17Surface water, Monitoring and reporting
  69. D13

    Receiving waters measured from Monitoring Point D specified in Table D3 - Receiving waters monitoring sites must not exceed the corresponding Limit B specified in Table D4 - Water quality objectives for receiving waters on any three consecutive sampling occasions. Table D4 - Water quality objectives for receiving waters Quality characteristic Water quality limit A Water quality limit B pH (pH units) NA 6.5 (minimum) [1] NA 8.0 (maximum)[1] Electrical conductivity 2,900[2] 3,300 [3] (micro siemens per centimetre, -S/cm) 4.2[1] 28.6 [5] Turbidity (NTU) [4] [1] Local water guideline values for protection of aquatic ecosystems for lowland fresh waters as per Table 2F of Environmental Protection (Water) Policy 2009 Curtis Island, Calliope River and Boyne River Basins Environmental Values and Water Quality Objectives), published in November 2014.. [2] Limit based on 75th percentile of Monitoring Point D specific data from January 2011 to March 2018. [3] Limit based on 95th percentile of Monitoring Point D specific data from January 2011 to March 2018. [4] If turbidity at Monitoring Point C is greater than Monitoring Point D then no exceedance is to be recorded. [5] Limit based on 95th percentile of Monitoring Point C specific data from January 2011 to April 2017. OFFICIAL Permit Environmental authority EPML00658113

    page 17Surface water, Monitoring and reporting
  70. D14

    By 02 December 2021, the environmental authority holder must develop and implement a Receiving Environment Monitoring Program (REMP) in accordance with the Receiving Environment Monitoring program guideline for use with environmentally relevant activities under the Environmental Protection environmental values, quality and flows; and groundwater due to the mining activity. This must include monitoring the effects of the mine on the receiving environment periodically and while contaminants are being discharged from the site. For the purposes of the REMP, the receiving environment includes the waters of: - Larcom Creek; - East End Creek; - Machine Creek; - Jacobs Creek; - Scrub Creek; - Shultz Lagoon; and - Groundwater.

    page 18Groundwater, Monitoring and reporting
  71. D15

    A report outlining the findings of the REMP, including all monitoring results and interpretations must be prepared biennially and submitted to the administering authority on request. This must include as a minimum an assessment of background reference water quality, the condition of downstream water quality compared against water quality objectives, the suitability of current discharge limits to protect downstream environmental values; and changes in groundwater quality.

    page 18Groundwater, Monitoring and reporting
  72. D16

    A Water Management Plan must be developed by an appropriately qualified person and implemented by the environmental authority holder.

  73. D17

    An Erosion and Sediment Control Plan (ESCP) must be developed by an appropriately qualified person and implemented by the environmental authority holder to minimise erosion and the release of sediment to receiving waters and contamination of stormwater.

    page 18Surface water, Land and soil
  74. D18

    The extraction of groundwater must not cause environmental harm to the terrestrial groundwater dependant ecosystems specified in Table D5 - Identified Terrestrial Groundwater Dependant Ecosystems or any groundwater dependant ecosystems outside of the zone of influence as depicted in Figure 4: Groundwater Zone of Influence. Table D5 - Identified Terrestrial Groundwater Dependant Ecosystems GDE Latitude Longitude 150.96963 Terrestrial GDE[1] -23.85373 [1] http://www.bom.gov.au/water/groundwater/gde/map.shtml

    page 18Groundwater
  75. D19

    By 02 December 2021, a Groundwater Monitoring and Management Program must be developed, documented and implemented by an appropriately qualified person. OFFICIAL Permit Environmental authority EPML00658113

    page 18Groundwater, Monitoring and reporting
  76. D20

    The Groundwater Monitoring and Management Program required by condition D19 must: a) identify potential sources of contamination to groundwater from the activity; and b) ensure that all potential groundwater impacts due to the activity are identified, monitored and mitigated; and c) document sampling and monitoring methodology; and d) ensure that adequate groundwater monitoring and data analysis is undertaken to achieve the following objectives: i. detect any impacts to groundwater levels due to the activity; and ii. detect any impacts to groundwater quality due to the activity; and iii. determine compliance with condition D18; and iv. determine trends in groundwater quality; and e) include an appropriate quality assurance and quality control program; and f) include validation of the calibrated transient groundwater model; and g) include a review process to identify improvements to the program that includes addressing any comments provided by the administering authority.

    page 19Groundwater, Monitoring and reporting
  77. D21

    The Groundwater Monitoring and Management Program required by condition D19 must be reviewed by 30 June each year by an appropriately qualified person to determine if it continues to meet the requirements stated in condition D20.

    page 19Groundwater, Monitoring and reporting
  78. D22

    Groundwater quality and standing water level must be monitored: a) at the monitoring points specified in Table D6 - Groundwater monitoring locations and frequency; and b) at the monitoring frequencies specified in Table D6 - Groundwater monitoring locations and frequency; and c) for the quality characteristics identified in Table D7 - Groundwater quality limits for the aquifer in which the bore is located OFFICIAL Permit Environmental authority EPML00658113 Table D6 - Groundwater monitoring locations and frequency Location (GDA94) Screened Monitoring Frequency Latitude Longitude interval RL Monitoring Point[1] Surface Standing Groundwater RL (m)[2] (m) Water Quality Level Limestone monitoring bores - Groundwater Quality within zone of influence DHH96-29 -23.872779 150.974047 36 20-36 DHH96-30 -23.874528 150.971084 20 15-27 DHH96-7 -23.900377 150.965663 50 8-50 Quarterly DHH96-20 -23.868636 150.953004 45 33-45 DHH96-25 -23.871112 150.969518 41.3 28-41.3 Volcaniclastic monitoring bores - Groundwater Quality within zone of influence DHH96-39 -23.888283 150.959185 TBA TBA Quarterly DHH96-14 -23.879067 150.941706 50 20-50 Subterranean Fauna Monitoring Bores DHH96-41 -23.891462 150.972234 36.67 TBA DHH96-33 TBA TBA TBA TBA EE Mine Forest Bore -23.874363 150.967503 TBA TBA SE DHH96-30 -23.874528 150.971084 20 15-27 Quarterly DHH96-29 -23.872779 150.974047 36 20-36 DHH96-7 -23.900377 150.965663 50 8-50 DHH97-6 -23.884431 150.969634 TBA TBA

    page 19Groundwater, Biodiversity, Monitoring and reporting
  79. B100

    -23.847465 150.951668 54.8 TBA Drawdown/GDE Monitoring Bores Limestone Compliance bores - Groundwater Levels and Quality DHH96-5 -23.852414 150.981157 44.77 10-50 Quarterly RC11-09 -23.798363 150.906876 30.487 24-36 Quarterly. Shultz lagoon 1 TBA TBA TBA TBA Shultz lagoon 2 TBA TBA TBA TBA Shultz lagoon 3 TBA TBA TBA TBA Volcaniclastic Compliance bores - Groundwater Levels and Quality DHH96-1 [3] -23.858826 150.974402 51.65 30-50 DHH96-2 [3] -23.855962 150.969479 51.85 0-20 DHH96-10 -23.87511 150.992037 41.51 27-50 DHH97-1A -23.858226 150.924669 67.662 10.3-19 Quarterly RC11-07 -23.832943 150.895126 71.183 30-100 RC11-13 -23.918103 150.996597 33.417 12-31 RC11-15 -23.896588 151.010276 44.975 18-76 RC11-17 -23.819972 150.96685 70.27 50-60 OFFICIAL Permit Environmental authority EPML00658113 Location (GDA94) Screened Monitoring Frequency Latitude Longitude interval RL Monitoring Point[1] Surface Standing Groundwater RL (m)[2] (m) Water Quality Level RC11-19 -23.88478 150.931748 63.13 70-100 RC11-20 -23.901544 150.936513 62.887 16-32 RC11-21 -23.925181 150.924282 62.596 14-32 Southern New Bore 1 TBA TBA TBA TBA Quarterly. Southern New Bore 2 TBA TBA TBA TBA [1] Locations depicted in Figure 3 -Groundwater monitoring locations. [2] RL must be measured to the nearest 5cm from the top of the bore casing. [3] Terrestrial GDE specific monitoring bore TBA To be advised to the administering authority by 02 March 2022.

    page 20Groundwater, Monitoring and reporting
  80. D23

    The activity must not cause a deterioration of groundwater quality.

    page 21Groundwater
  81. D24

    Groundwater measured from any compliance bore specified in Table D6 - Groundwater monitoring locations and frequency must not exceed the corresponding Limit A specified in Table D7 - Groundwater quality limits on any five consecutive sampling occasions.

    page 21Groundwater, Monitoring and reporting
  82. D25

    Groundwater measured from any compliance bore specified in Table D6 - Groundwater monitoring locations and frequency must not exceed the corresponding Limit B specified in Table D7 - Groundwater quality limits on any three consecutive sampling occasions.

    page 21Groundwater, Monitoring and reporting
  83. D26

    If groundwater measured from any compliance bore specified in Table D6 - Groundwater monitoring locations and frequency exceeds the corresponding Limit B specified in Table D7 - Groundwater quality limits on any one sampling occasion the environmental authority holder must resample the groundwater within the compliance bore for all exceeding parameters within ten business days of receipt of results. OFFICIAL Permit Environmental authority EPML00658113 Table D7 - Groundwater quality limits Quality Characteristic Monitoring Point pH (pH units) Electrical Conductivity (micro siemens Major ions[1] per centimetre (-s/cm)) (milligrams per DHH96-5 RC11-09 Range Maximum Maximum litre (mg/L)) Shultz lagoon 1 Limit A[2] Limit B[3] Shultz lagoon 2 21,912 24,151 NA Shultz lagoon 3 DHH96-1 [3] 5,830 5,920 TBA TBA TBA TBA TBA TBA 26,800 33,683 DHH96-2 [3] 9,880 13,413 DHH96-10 4,784 4,817 DHH97-1A 6.5 (minimum) 284 311 For interpretation RC11-07 8.0 (maximum) 5,840 6,740 purposes only. RC11-13 11,394 11,406 RC11-15 9,090 9,997 RC11-17 10,000 11,117 RC11-19 3,970 4,120 RC11-20 3,630 4,372 RC11-21 1,660 1,787 Southern New Bore 1 TBA TBA Southern New Bore 2 TBA TBA [1] Major ions include calcium, magnesium, sodium, potassium, bicarbonate, chloride, and sulphate. [2] Limit A has been determined from the 80th percentile of the specific bore historical groundwater quality data up to March 2017. [3] Limit B has been determined from the 95th percentile of the specific bore historical groundwater quality data up to March 2017. TBA To be advised to the administering authority by 02 November 2023.

    page 21Groundwater, Monitoring and reporting
  84. D27

    If the standing water level of groundwater measured at any compliance bore specified in Table D6 - Groundwater monitoring locations and frequency is less than any of the corresponding trigger levels specified in Table D8 - Groundwater monitoring trigger levels, the environmental authority holder must: a) notify the administering authority within 24 hours; and b) conduct an investigation into the cause within ten business days; and c) if the mining activities are identified as a potential cause or contributor, take immediate action to ensure compliance with condition D18 of this environmental authority. Table D8 - Drawdown/GDE Groundwater monitoring trigger levels Monitoring Unit Trigger Levels [1] Limit Type Point Minimum Limestone Compliance bores - Groundwater Levels Minimum DHH96-5 38.2 RC11-09 24.6 Shultz lagoon 1 SWL m RL TBA Shultz lagoon 2 TBA Shultz lagoon 3 TBA Volcaniclastic Compliance bores - Groundwater Levels DHH96-1 [2] 44.1 DHH96-2 [2] 44.8 DHH96-10 34.5 DHH97-1A 60.4 RC11-07 55.3 RC11-13 24.2 RC11-15 SWL m RL 43.6 RC11-17 49.8 RC11-19 56.0 RC11-20 48.7 RC11-21 52.7 Southern New Bore 1 TBA Southern New Bore 2 TBA [1] 5th percentile minus 0.5 metre [2] Terrestrial GDE specific monitoring bores TBA To be advised to the administering authority by 02 November 2023.

    page 23Groundwater, Monitoring and reporting
  85. D28

    Groundwater monitoring bores must be : a) constructed and maintained in a manner that ensures the integrity of the bores to obtain representative groundwater samples from the target aquifer; and b) constructed, maintained and decommissioned in a manner that: i. prevents contaminants entering the groundwater; and ii. that maintains the hydogeological environment within the aquifer.

    page 24Groundwater, Monitoring and reporting
  86. D29

    A bore drill log must be kept for each groundwater monitoring bore which includes: a) bore identification reference and geographic coordinate location; b) specific construction information including but not limited to depth of bore, depth and length of casing, depth and length of screening and bore sealing details; c) standing groundwater level and water quality parameters including physical parameters and results of laboratory analysis for the possible trigger parameters; d) lithological data and stratigraphic interpretation by an appropriately qualified person to identify important features associated with groundwater monitoring; and e) target aquifer formation of the bore.

    page 24Groundwater, Monitoring and reporting
  87. D30

    Monitoring and sampling must be carried out in accordance with written procedures and must address the requirements of the latest version of the following documents unless otherwise approved by the administering authority: a) for waters and aquatic environments, the Queensland Government's Monitoring and Sampling Manual 2009 - Environmental Protection (Water) Policy 2009 b) for groundwater, Groundwater Sampling and Analysis - A Field Guide (2009:27 GeoCat#6890.1) and Australian Standard AS/NZS 5667.11:1998 Water Quality - Sampling - Guidance on sampling of groundwaters; c) for subterranean aquatic fauna, the Guideline for the Environmental Assessment of Subterranean Aquatic Fauna.

    page 24Groundwater, Biodiversity, Monitoring and reporting
  88. D31

    Prior to the commencement of pit development on ML80156, a Subterranean Fauna Monitoring and Management Program must be developed by an appropriately qualified person and implemented by the environmental authority holder.

    page 24Biodiversity, Monitoring and reporting
  89. D32

    The Subterranean Fauna Monitoring and Management Program required by condition D31 must include adequate monitoring of subterranean species of stygofauna and troglofauna in all groundwaters potentially impacted by the mining activities and must achieve the following objectives: a) Identify and describe subterranean fauna species present; b) In addition to condition D32(a), accurately describe and determine the distribution of the unique taxa found at bore locations EEUN2 and DHH96-41; c) Assess and describe predicted impacts to subterranean fauna identified; d) Recommend impact mitigation and minimisation measures for the fauna identified; e) Monitor and record the effects of the mining activity on the subterranean fauna species; f) Recommend actions, including timeframes for implementation, to ensure that any impacts to subterranean fauna not authorised under this environmental authority, are prevented. OFFICIAL Permit Environmental authority EPML00658113

    page 24Groundwater, Biodiversity, Monitoring and reporting
  90. D33

    If the standing water level of groundwater measured at any compliance bore specified in Table D6 - Groundwater monitoring locations and frequency is less than any of the corresponding trigger levels specified in Table D9 - Subterranean fauna trigger levels, the environmental authority holder must: a) notify the administering authority within 24 hours; and b) review the Subterranean Fauna Monitoring and Management Program required by condition

    page 25Groundwater, Biodiversity, Monitoring and reporting
  91. D31

    within ten business days, particularly the requirements of condition D32 c), d), e), and f). Table D9 - Subterranean fauna trigger levels Monitoring Unit Trigger Levels [1] Limit Type Point DHH96-30 SWL m RL 24.1 Minimum DHH97-6 25.1 EE Mine Forest Bore SE 20.4 DHH96-29 31.2 DHH96-41 29.9 DHH96-7 32.7 DHH96-33 TBA DHH96-39 42.7

    page 25Groundwater, Biodiversity, Monitoring and reporting
  92. B100

    28.7 [1] 5th percentile minus 0.5 metre END OF CONDITIONS FOR SCHEDULE D OFFICIAL Permit Environmental authority EPML00658113 Schedule E - Land

  93. E1

    Treated sewage effluent may only be released to land in accordance with the conditions of this environmental authority at the following locations: a) Within the nominated area(s) identified in Figure 5: Location of sewage effluent disposal area; and b) Other land for the purpose of dust suppression and/or firefighting.

  94. E2

    The release of treated sewage effluent to land must not exceed the release limits stated in Table E1 - Contaminant release limits to land. Table E1 - Contaminant release limits to land Quality Characteristic Unit Release Limit type Monitoring limit frequency Five-day biochemical oxygen demand mg/L 20 Maximum Monthly (BOD) Total suspended solids mg/L 30 Maximum Nitrogen mg/L 30 Maximum Phosphorus mg/L 15 Maximum E-coli organisms/100mL 1000 Maximum pH pH units 6.5 - 9.0 Range

    page 26Monitoring and reporting
  95. E3

    The application of treated effluent to land must be carried out in a manner that: a) Vegetation is not damaged; and b) There is no surface ponding of effluent; and c) There is no run-off of effluent.

    page 26Biodiversity
  96. E4

    If areas irrigated with effluent are accessible to employees or the general public, prominent signage must be provided advising that effluent is present and care should be taken to avoid consuming or otherwise coming into unprotected contact with the effluent.

  97. E5

    All sewage effluent released to land must be monitored at the monitoring frequency and for the quality characteristics specified in Table E1 - Contaminant release limits to land.

    page 26Monitoring and reporting
  98. E6

    The monthly volume of effluent released to land must be measured and recorded.

  99. E7

    When circumstances prevent the irrigation or beneficial reuse of treated effluent such as during or following rain events, waters must be directed to a wet weather storage or alternative measures must be taken to store/lawfully dispose of effluent.

  100. E8

    A minimum area of 10m2 of land, excluding any necessary buffer zones, must be utilised for the irrigation and/or beneficial reuse of treated sewage effluent.

  101. E9

    The release of contaminated water to land, other than treated sewage effluent in accordance with the conditions of this environmental authority, must only occur from the release points specified in Table E2 - Contaminant release to land locations. OFFICIAL Permit Environmental authority EPML00658113 Table E2 - Contaminant release to land locations Release Location (GDA94) Contaminated water source[1] point[1] Latitude Longitude (RP) E -23.879990 150.949572 East End mining operations, including clay dumps and haul roads, discharging at the spillway from the western sediment pond E. F -23.886765 150.966112 East End mining operations, including clay dumps and haul roads, discharging at the spillway from southern sediment pond F. [1] Locations depicted in Figure 2 - Release point and surface water monitoring locations.

    page 26Surface water, Regulated structures, Land and soil, Monitoring and reporting
  102. E10

    The release of contaminants to lands in accordance with condition E9 must not exceed the release limits for each quality characteristic stated in Table E3 - Contaminant release to land limits when measured at the release points specified in Table E2 - Contaminant release to land locations. Table E3 - Contaminant release to land limits Quality characteristic Release limit Monitoring frequency 5,000 Electrical Conductivity (EC) During a release (sample must be taken within (micro Siemens per 6.5 (minimum) 24 hours of commencement of release but before centimetre, -s/cm) 8.5 (maximum) cessation of the release). pH (pH units)

    page 27Surface water, Monitoring and reporting
  103. E11

    The release of contaminants to land in accordance with condition E9 must be monitored at the release points specified in Table E2 - Contaminant release to land locations and depicted in Figure 2 - Release points and surface water monitoring locations, for each quality characteristic and at the monitoring frequency specified in Table E3 - Contaminant release to land limits.

    page 27Surface water, Monitoring and reporting
  104. E12

    The release of contaminants to land in accordance with condition E9 must be carried out in a manner that: a) Drainage to groundwater and subsurface flows of contaminants to surface waters are prevented; and b) Surface pondage and run-off of contaminants is prevented; and c) Degradation of soil structure is minimised; and d) Soil sodicity and the build-up of heavy metals and metalloids in the soil and subsoil is minimised.

    page 27Groundwater, Surface water, Land and soil
  105. E13

    Land disturbed by mining activities must be rehabilitated in accordance with Table E4 - Rehabilitation requirements. OFFICIAL Permit Environmental authority EPML00658113 Table E4 - Rehabilitation requirements Mine Rehabilitation Rehabilitation Indicators Completion criteria domain goal objectives Mine pit Safety assessment Validation in rehabilitation report that slopes slopes that Safe to Site is safe for of slopes that are are safe and predictions about future safety are greater humans humans and greater than 30- than 30- and wildlife animals now and and greater than Validation in water quality report that and in the foreseeable 5m in height surface and groundwater objectives are greater future met. than 5m End of pipe and in height Non-polluting Surface and receiving Evidence in Final Rehabilitation Report Mine water groundwater that waters meet that appropriate risk assessment has been storages Stable leave the lease will environmental undertaken and control measures are in Able to sustain aim to meet or authority place. Mine an agreed improve the water conditions. Final Rehabilitation Report will be prepared workings, post-mining quality objectives of as per administering authority rehabilitation void, water land use the receiving Geotechnical guidelines including: storages waters. Current studies of - The results of a site investigation Mine and future water workings, high - The results of a residual risk workings quality parameters walls and voids above will be maintained - Tree density assessment (including estimation of

    page 27Rehabilitation, Groundwater, Monitoring and reporting
  106. E14

    Rehabilitation must commence progressively in accordance with the plan of operations.

    page 29Rehabilitation
  107. E15

    The environmental authority holder must minimise the potential for contamination of land by hazardous contaminants. END OF CONDITIONS FOR SCHEDULE E OFFICIAL Permit Environmental authority EPML00658113 Definitions Key terms and/or phrases used in this document are defined in this section. Where a term is not defined, the definition in the Environmental Protection Act 1994, its regulations or environmental protection policies must be used. If a word remains undefined it has its ordinary meaning. Airblast overpressure energy transmitted from the blast site within the atmosphere in the form of pressure waves. The maximum excess pressure in this wave, above ambient pressure is the peak Airblast overpressure measured in decibels linear (dBL). Annual exceedance probability or AEP the probability that at least one event in excess of a particular magnitude will occur in any given year. Annual inspection report means an assessment prepared by a suitably qualified and experienced person containing details of the assessment against the most recent consequence assessment report and design plan (or system design plan): a) against recommendations contained in previous annual inspections reports b) against recognised dam safety deficiency indicators c) for changes in circumstances potentially leading to a change in consequence category d) for conformance with the conditions of this authority e) for conformance with the `as constructed' drawings f) for the adequacy of the available storage in each regulated dam, based on an actual observation or observations taken after 31 May each year but prior to 1 November of that year, of accumulated sediment, state of the containment barrier and the level of liquids in the dam (or network of linked containment systems) g) for evidence of conformance with the current operational plan. Appropriately qualified person a person who has professional qualifications, training, skills or experience relevant to the nominated subject matter and can give authoritative assessment, advice and analysis on performance relating to the subject matter using the relevant protocols, standards, methods or literature. Assessed and assessment by a suitably qualified and experienced person in relation to a consequence assessment of a dam, means that a statutory declaration has been made by that person and, when taken together with any attached or appended documents referenced in that declaration, all of the following aspects are addressed and are sufficient to allow an independent audit of the assessment: a) exactly what has been assessed and the precise nature of that determination; b) the relevant legislative, regulatory and technical criteria on which the assessment has been based; c) the relevant data and facts on which the assessment has been based, the source of that material, and the efforts made to obtain all relevant data and facts; and d) the reasoning on which the assessment has been based using the relevant data and facts,

    page 29Regulated structures, Noise and vibration, Waste, Land and soil, Monitoring and reporting

Instrument text by page (numbering incomplete)

Numbering in this instrument has gaps, so its full text is also shown page by page.

  1. Page 1

    OFFICIAL Permit Environmental Protection Act 1994 Environmental authority EPML00658113 This environmental authority is issued by the administering authority under Chapter 5 of the Environmental Protection Act 1994. Environmental authority number: EPML00658113 Environmental authority takes effect on 27 May 2025. The anniversary date of this environmental authority is 8 October each year. An annual return will be due each year on 01 April. Environmental authority holder(s) Name(s) Registered address Cement Australia (Exploration) Pty Ltd 18 Station Ave Cement Australia (Queensland) Pty Limited DARRA QLD 4076 40 McDougall Street MILTON QLD 4064 Environmentally relevant activity and location details Environmentally relevant activity/activities Location(s) ML3629 Schedule 3 - 21 - A mining activity that is an ineligible ML3630 ERA, other than a mining activity mentioned in items ML3631 9 to 20 ML3632 ML3659 ML7629 ML80127 ML80156 ML80002

  2. Page 2

    OFFICIAL Permit Environmental authority EPML00658113 Environmentally relevant activity/activities Location(s) Ancillary 63 - Sewage Treatment - 1(a-ii) - Operating ML3629 sewage treatment works, other than no-release works, ML3630 with a total daily peak design capacity of 21 to 100EP ML3631 - otherwise ML3632 ML3659 ML7629 ML80002 ML80127 Ancillary 33 - Crushing, milling, grinding or screening ML3659 - Crushing, grinding, milling or screening more than ML3631 5000t of material in a year Additional information for applicants Environmentally relevant activities The description of any environmentally relevant activity (ERA) for which an environmental authority (EA) is issued is a restatement of the ERA as defined by legislation at the time the EA is issued. Where there is any inconsistency between that description of an ERA and the conditions stated by an EA as to the scale, intensity or manner of carrying out an ERA, the conditions prevail to the extent of the inconsistency. An EA authorises the carrying out of an ERA and does not authorise any environmental harm unless a condition stated by the EA specifically authorises environmental harm. A person carrying out an ERA must also be a registered suitable operator under the Environmental Protection Act 1994 (EP Act). Contaminated land It is a requirement of the EP Act that an owner or occupier of contaminated land give written notice to the administering authority if they become aware of the following: - the happening of an event involving a hazardous contaminant on the contaminated land (notice must be given within 24 hours); or - a change in the condition of the contaminated land (notice must be given within 24 hours); or - a notifiable activity (as defined in Schedule 3) having been carried out, or is being carried out, on the contaminated land (notice must be given within 20 business days) that is causing, or is reasonably likely to cause, serious or material environmental harm. For further information, including the form for giving written notice, refer to the Queensland Government website www.qld.gov.au, using the search term `duty to notify'.

    Waste, Monitoring and reporting
  3. Page 3

    OFFICIAL Permit Environmental authority EPML00658113 Take effect Please note that, in accordance with section 200 of the EP Act, an EA has effect: a) if the authority is for a prescribed ERA and it states that it takes effect on the day nominated by the holder of the authority in a written notice given to the administering authority - on the nominated day; or b) if the authority states a day or an event for it to take effect-on the stated day or when the stated event happens; or c) otherwise on the day the authority is issued. However, if the EA is authorising an activity that requires an additional authorisation (a relevant tenure for a resource activity, a development permit under the Planning Act 2016 or an SDA Approval under the State Development and Public Works Organisation Act 1971), this EA will not take effect until the additional authorisation has taken effect. If this EA takes effect when the additional authorisation takes effect, you must provide the administering authority written notice within 5 business days of receiving notification of the related additional authorisation taking effect. The anniversary day of this environmental authority is the same day each year as the original take effect date unless you apply to change the anniversary day. The payment of the annual fee will be due each year on this day. An annual return will be due each year on 01 April. If you have incorrectly claimed that an additional authorisation is not required, carrying out the ERA without the additional authorisation is not legal and could result in your prosecution for providing false or misleading information or operating without a valid environmental authority. 27 May 2025 Signature Date Teale Gibbs Enquiries: Tourism, Science and Innovation PO Box 7230, CAIRNS QLD 4870 Delegate of the administering authority Phone: (07) 4222 5352 Environmental Protection Act 1994 Email: ESCairns@des.qld.gov.au Privacy statement Pursuant to section 540 of the EP Act, the Department is required to maintain a register of certain documents and information authorised under the EP Act. A copy of this document will be kept on the public register. The register is available for inspection by members of the public who are able take extracts, or copies of the documents from the register. Documents that are required to be kept on the register are published in their entirety, unless alteration is required by the EP Act. There is no general discretion allowing the Department to withhold documents or information required to be kept on the public register. For more information on the Department's public register, search `public register' at www.qld.gov.au. For queries about privacy matters please email privacy@des.qld.gov.au or telephone 13 74 68.

    Monitoring and reporting
  4. Page 4

    OFFICIAL Permit Environmental authority EPML00658113 Obligations under the Environmental Protection Act 1994 In addition to the requirements found in the conditions of this environmental authority, the holder must also meet their obligations under the EP Act, and the regulations made under the EP Act. For example, the holder must comply with the following provisions of the Act: - general environmental duty (section 319) - duty to notify environmental harm (section 320-320G) - offence of causing serious or material environmental harm (sections 437-439) - offence of causing environmental nuisance (section 440) - offence of depositing prescribed water contaminants in waters and related matters (section 440ZG) - offence to place contaminant where environmental harm or nuisance may be caused (section 443) Other permits required This permit only provides an approval under the Environmental Protection Act 1994. In order to lawfully operate you may also require permits / approvals from your local government authority, other business units within the department and other State Government agencies prior to commencing any activity at the site. For example, this may include permits / approvals with your local Council (for planning approval), the Department of Transport and Main Roads (to access state controlled roads), the Department of Resources (to clear vegetation), and the Department of Agriculture and Fisheries (to clear marine plants or to obtain a quarry material allocation).

    Biodiversity, Monitoring and reporting
  5. Page 5

    OFFICIAL Permit Environmental authority EPML00658113 Conditions of environmental authority Schedule A - General A1 This environmental authority authorises environmental harm referred to in the conditions. Where there is no condition or this environmental authority is silent on a matter, the lack of a condition or silence does not authorise environmental harm. A2 In carrying out the mining activity authorised by this environmental authority, the environmental authority holder must comply with the authorised disturbance areas listed in Table A1 - Authorised disturbance and as depicted in Figure 1 - Project Infrastructure Layout Mine Area and Support Infrastructure. Table A1 - Authorised disturbance Mine Feature Name Location[1] (GDA2020, Maximum Description / Purpose decimal degrees[2]) Disturbance Water Storage / Includes: water storages, Settling Ponds Latitude Longitude Area (ha) sediment settling ponds. Void / Mine Workings / Haul -23.87743 150.96314 11 Voids, haul roads, mine Roads workings, access roads -23.87779 150.95840 209 Includes: overburden and spoil dumps Spoil Dumps -23.88061 150.95264 53 Includes: Stockpiles, Crushing Plant, Offices, Workshops, Rail Stockpiling/Crushing/Loading -23.87646 150.95848 37 Loop and Infrastructure -23.87406 150.96226 -23.87551 150.96747 [1] Coordinates indicate location of mine feature not boundaries. [2] Decimal degrees to be provided to a minimum of 5 decimal places. A3 The environmental authority holder must: a) Install all measures, plant and equipment necessary to ensure compliance with the conditions of this environmental authority; and b) Maintain such measures, plant and equipment in a proper and efficient manner; and c) Operate such measures, plant and equipment in a proper and efficient manner; and, d) Ensure all instruments and devices used for the measurement or monitoring of any parameter under any condition of this environmental authority are properly calibrated. A4 All flammable, corrosive and combustible liquids, including petroleum products, must be stored and handled in accordance with: a) The latest edition of AS1940--The storage and handling of flammable and combustible liquids where applicable; b) The current Australian Standard where applicable; or c) Where no relevant Australian Standard exists, store such materials within an on-site containment system sufficient to prevent release to the receiving environment.

    Land and soil, Monitoring and reporting
  6. Page 6

    OFFICIAL Permit Environmental authority EPML00658113 A5 Financial assurance must be lodged in the amount, the form, and within the time required by the administering authority. A6 Any records kept or created in relation to this environmental authority must be: a) kept for a period of at least five years; and b) provided to the administering authority on request; and c) provided to the administering authority in the format requested. A7 An appropriately qualified person(s) must monitor and record all indicator(s) required by and in accordance with this environmental authority. A8 When required by the administering authority, monitoring must be undertaken in the manner prescribed by the administering authority to investigate a complaint arising from the activity. The monitoring results must be recorded. A9 The following must be recorded in relation to all monitoring required under a condition of this environmental authority: a) The date and time when the sample was taken; b) The location where the sample was taken; c) The results of all monitoring and details of exceedances of the conditions of this environmental authority; and d) Any other pertinent details of relevance to interpreting the sample results (i.e. stream or release flow rate, wind, conditions, atmospheric conditions, any relevant observations such as odour or colouration). A10 The environmental authority holder must implement and maintain a risk management system for mining activities which mirrors the content requirement of the Standard for Risk Management (ISO31000:2009), or the Standard for Environmental Management Systems (ISO14001), or the latest edition of an Australia standard for risk management, to the extent relevant to environmental management. A11 The environmental authority holder must notify the administering authority within twenty four (24) hours of becoming aware of any incident or event which does or may contravene a condition of this environmental authority. Notification to the administering authority must be provided to the administering authority Pollution Hotline on 1300 130 372 and PollutionHotline@ehp.qld.gov.au. A12 Within ten (10) business days following the initial notification of an incident or event, or receipt of monitoring results, whichever is the latter, further written advice must be provided to the administering authority, including the following: a) Results and interpretation of any samples taken and analysed; and b) Outcomes of actions taken at the time to prevent or minimise unlawful environmental harm; and c) Proposed actions to prevent recurrence of the emergency or incident.

    Air, Monitoring and reporting
  7. Page 7

    OFFICIAL Permit Environmental authority EPML00658113 A13 The environmental authority holder must record all environmental complaints received about the mining activities including: a) Name, address and contact number of the complainant; b) Time and date of complaint; c) Reasons for the complaint; d) Investigations undertaken; e) Conclusions formed; f) Actions taken to resolve the complaint; g) Any abatement measures implemented; and h) Person responsible for resolving the complaint. A14 Compliance with the conditions of this environmental authority must be audited at regular intervals not exceeding once every three (3) years. The audit must be conducted by a suitably qualified third party auditor. The environmental authority holder must submit a final version of the auditor's report to the administering authority within ninety (90) days of completing the audit. A15 All waste generated as part of the mining activities must be lawfully reused, recycled, or removed to an off-site facility that can lawfully accept the waste. A16 Scrap tyres stored awaiting disposal or transport for take-back and recycling, or waste to energy options must be stored in stable stacks and at least 10 metres away from any other scrap tyre storage area, or combustible or flammable material, including vegetation. A17 All reasonable and practicable fire prevention measures must be implemented, including removal of grass and other materials within a 10 metre radius of the scrap tyre storage area. A18 Where no feasible recycling or waste-to-energy options are available, disposing of scrap tyres resulting from the mining activities in spoil emplacements is acceptable, provided tyres are placed as deep in the spoil as reasonably practicable. A19 Scrap tyres resulting from the mining activities disposed within the operational land must not impede saturated aquifers or compromise the stability of the consolidated landform. A20 The consequence category of any structure must be assessed by a suitably qualified and experienced person in accordance with the Manual for Assessing Consequence Categories and Hydraulic Performance of Dams (EM635) at the following times: a) Prior to the design and construction of the structure, if it is not an existing structure; or b) Prior to any change in its purpose or the nature of its stored contents. A21 A consequence assessment report and certification must be prepared for each structure assessed and the report may include a consequence assessment for more than one structure. A22 Certification must be provided by the suitably qualified and experienced person who undertook the assessment, in the form set out in the Manual for Assessing Consequence Categories and Hydraulic

    Groundwater, Regulated structures, Waste, Biodiversity, Monitoring and reporting
  8. Page 8

    OFFICIAL Permit Environmental authority EPML00658113 A23 Except for an existing structure, all regulated structures must be designed by, and constructed under the supervision of, a suitably qualified and experienced person in accordance with the requirements of the A24 Except for an existing structure, construction of a regulated structure is prohibited unless a) The environmental authority holder has submitted a consequence category assessment report and certification to the administering authority; b) Certification for the design, design plan and the associated operating procedures has been certified by a suitably qualified and experienced person in compliance with the relevant condition of this environmental authority. A25 Except for an existing structure, certification must be provided by the suitably qualified and experienced person who oversees the preparation of the design plan in the form set out in the Manual for be recorded in the Register of Regulated Structures. A26 Except for an existing structure, regulated structures must: a) Be designed and constructed in compliance with the Manual for Assessing b) Be designed and constructed with due consideration given to ensuring that the design integrity would not be compromised on account of: i. floodwaters from entering the regulated dam from any watercourse or drainage line; ii. wall failure due to erosion by floodwaters arising from any watercourse or drainage line. c) Have the floor and sides of the dam designed and constructed to prevent or minimise the passage of the wetting front and any entrained contaminants through either the floor or sides of the dam during the operational life of the dam and for any period of decommissioning and rehabilitation of the dam. A27 Except for an existing structure, certification by the suitably qualified and experienced person who supervises the construction must be submitted to the administering authority on the completion of construction of the regulated structure, and state that: a) The `as constructed' drawings and specifications meet the original intent of the design plan for that regulated structure; b) Construction of the regulated structure is in accordance with the design plan. A28 All affected persons must be provided with a copy of the emergency action plan in place for each regulated structure: a) For existing structures that are regulated structures, within ten (10) business days of this condition taking effect; b) Prior to the operation of the new regulated structure; and c) If the emergency action plan is amended, within five (5) business days of it being amended.

    Rehabilitation, Surface water, Regulated structures, Land and soil, Monitoring and reporting
  9. Page 9

    OFFICIAL Permit Environmental authority EPML00658113 A29 Operation of a regulated structure, except for an existing structure, is prohibited unless the environmental authority holder has submitted to the administering authority a) One (1) paper copy and one electronic copy of the design plan and certification of the `design plan' in accordance with condition A24; b) A set of `as constructed' drawings and specifications; c) Certification of those `as constructed drawings and specifications' in accordance with condition A27; d) Where the regulated structure is to be managed as part of an integrated containment system for the purpose of sharing the design storage allowance (DSA) volume across the system, a copy of the certified system design plan; e) The requirements of this authority relating to the construction of the regulated structure have been met; f) The holder has entered the details required under this authority, into a Register of Regulated Structures; and g) There is a current operational plan for the regulated structure. A30 Each regulated structure must be maintained and operated, for the duration of its operational life until decommissioned and rehabilitated, in a manner that is consistent with the current operational plan and, if applicable, the current design plan and associated certified `as constructed' drawings. A31 For regulated structures that have not been certified as low consequence category for `failure to contain - overtopping', the mandatory reporting level (MRL) must be marked on a regulated dam in such a way that during routine inspections of that dam, it is clearly observable. A32 For regulated structures that have not been certified as low consequence category for `failure to contain - overtopping', the environmental authority holder must, as soon as practical but within forty-eight (48) hours of becoming aware, notify the administering authority when the level of the contents of a regulated dam reaches the MRL. A33 For regulated structures that have not been certified as low consequence category for `failure to contain - overtopping', the environmental authority holder must, immediately on becoming aware that the MRL has been reached, act to prevent the occurrence of any unauthorised discharge from the regulated dam. A34 For regulated structures that have not been certified as low consequence category for `failure to contain - overtopping', the environmental authority holder must record any changes to the MRL in the Register of Regulated Structures. A35 The environmental authority holder must assess the performance of each regulated dam or linked containment system over the preceding November to May period based on actual observations of the available storage in each regulated dam or linked containment system taken prior to 1 July of each year. A36 By 1 November of each year, storage capacity must be available in each regulated dam (or network of linked containment systems with a shared DSA volume), to meet the DSA volume for the dam (or network of linked containment systems).

    Rehabilitation, Regulated structures, Monitoring and reporting
  10. Page 10

    OFFICIAL Permit Environmental authority EPML00658113 A37 The environmental authority holder must, as soon as possible but within forty-eight (48) hours of becoming aware that the regulated dam (or network of linked containment systems) will not have the available storage to meet the DSA volume on 1 November of any year, notify the administering authority. A38 The environmental authority holder must, immediately on becoming aware that a regulated dam (or network of linked containment systems) will not have the available storage to meet the DSA volume on 1 November of any year, act to prevent the occurrence of any unauthorised discharge from the regulated dam or linked containment systems. A39 Each regulated structure must be inspected each calendar year by a suitably qualified and experienced person. A40 At each annual inspection, the condition and adequacy of all components of the regulated structure must be assessed and a suitably qualified and experienced person must prepare an annual inspection report containing details of the assessment and include a recommendations section, with any recommended actions to ensure the integrity of the regulated structure or a positive statement that no recommendations are required. A41 The suitably qualified and experienced person who prepared the annual inspection report must certify the report in accordance with the Manual for Assessing Consequence Categories and Hydraulic A42 The environmental authority holder must within twenty (20) business days of receipt of the annual inspection report, provide to the administering authority: a) The recommendations section of the annual inspection report; b) If applicable, any actions being taken in response to those recommendations; and c) If, following receipt of the recommendations and (if applicable) recommended actions, the administering authority requests a copy of the annual inspection report from the environmental authority holder, provide this to the administering authority within ten (10) business days of receipt of the request. A43 The environmental authority holder must provide a copy of any reports, documentation and certifications prepared under this authority, including but not limited to any Register of Regulated Structures, consequence assessment, design plan and other supporting documentation, to a new environmental authority holder on transfer of this activity.

    Regulated structures, Monitoring and reporting
  11. Page 11

    OFFICIAL Permit Environmental authority EPML00658113 A44 Regulated structures must not be abandoned but be either: a) Decommissioned and rehabilitated to achieve compliance with Schedule E of this environmental authority; or b) Be left in-situ for a use by the landholder provided that: i. it no longer contains contaminants that will migrate into the environment; ii. it contains water of a quality that is demonstrated to be suitable for its intended use(s); and iii. the environmental authority holder and the landholder agree in writing that the: 1. dam will be used by the landholder following the cessation of the environmentally relevant activity(ies); and 2. landholder is responsible for the dam, on and from an agreed date. A45 A Register of Regulated Structures must be established and maintained by the environmental authority holder for each regulated structure. A46 The environmental authority holder must provisionally enter the required information in the Register of Regulated Structures when a design plan for a regulated structure is submitted to the administering authority. A47 The environmental authority holder must make a final entry of the required information in the Register of Regulated Structures once compliance with condition A29 has been achieved. A48 The environmental authority holder must ensure that the information contained in the Register of Regulated Structures is current and complete on any given day. A49 All entries in the Register of Regulated Structures must be approved by the chief executive officer for the environmental authority holder, or their delegate, as being accurate and correct. A50 The environmental authority holder must, at the same time as providing the annual return, supply to the administering authority a copy of the records contained in the Register of Regulated Structures, in the electronic format required by the administering authority. END OF CONDITIONS FOR SCHEDULE A

    Rehabilitation, Regulated structures, Monitoring and reporting
  12. Page 12

    OFFICIAL Permit Environmental authority EPML00658113 Schedule B - Air B1 The release of dust or particulate matter, or both, resulting from the mining activity must not cause environmental harm to an environmental value for air. B2 When measured at any area or place outside of the mining lease boundary, airborne contaminants generated by the mining activities must not cause the following levels to be exceeded: a) Dust deposition of 120 milligrams per square metre per day, averaged over 1 month, when monitored in accordance with the most recent version of Australian Standard AS3580.10.1 Methods for sampling and analysis of ambient air - Determination of particulate matter - Deposited matter - Gravimetric method. b) A concentration of particulate matter with an aerodynamic diameter of less than 10 micrometres (PM10) suspended in the atmosphere of 50 micrograms per cubic metre over a 24-hour averaging time, for no more than five exceedances recorded each year, when monitored in accordance with the most recent version of either: i. Australian Standard AS3580.9.6 Methods for sampling and analysis of ambient air - Determination of suspended particulate matter - PM10 high volume sampler with size-selective inlet - Gravimetric method, or ii. Australian Standard AS3580.9.9 Methods for sampling and analysis of ambient air - Determination of particulate matter - PM10 low volume sampler - Gravimetric method. END OF CONDITIONS FOR SCHEDULE B

    Air, Monitoring and reporting
  13. Page 13

    OFFICIAL Permit Environmental authority EPML00658113 Schedule C - Acoustic C1 Noise generated by the mining activities must not exceed the specified levels in Table C1 - Noise limits when measured at any sensitive receptor. Table C1 - Noise limits Location Noise Monday to Saturday Sundays and Public Holidays level 7am to 6pm to 10pm to 9am to 6pm to 10pm to dB(A) 6pm 10pm 7am 6pm 10pm 9am measured as: Dwelling LAeq, Bkg + Bkg + Bkg + Bkg + Bkg + Bkg + adj, 1 5dBA 3dBA 3dBA 5dBA 3dBA 3dBA hMoauxr Bkg + Bkg + Bkg + Bkg + Bkg + Bkg + LpA, 1 5dBA hNoouisr e 10dBA 5dBA 10dBA 5dBA 5dBA Commercial Monday to Saturday Sundays and Public Holidays level 7am to 6pm to 10pm to 7am to 6pm to 10pm to dB(A) 6pm 10pm 7am 6pm 10pm 7am measured as: LAeq, Bkg + Bkg + Bkg + Bkg + Bkg + Bkg + adj, 1 10dBA 5dBA 5dBA 10dBA 5dBA 5dBA hMoauxr Bkg + Bkg + Bkg + Bkg + Bkg + Bkg + LpA, 1 15dBA 10dBA 10dBA 15dBA 10dBA 10dBA A - A weightehdour Bkg = Background dB - Decibel LAeq - the A-weighted equivalent continuous Lp of the sample time T Lp - Sound pressure level Associated requirements: C2 The environmental authority holder must ensure that blasting does not cause the limits for peak particle velocity and air blast overpressure in Table C2 - Blasting noise limits to be exceeded when measured at any sensitive receptor.

    Noise and vibration
  14. Page 14

    OFFICIAL Permit Environmental authority EPML00658113 Table C2 - Blasting noise limits Blasting noise limits Sensitive receptor blasting noise limits Airblast overpressure 8am to 5pm Monday to Saturday Other times and Ground vibration peak Public holidays particle velocity 115dB (Linear) Peak for 9 out of 10 consecutive blasts No blasting initiated and not greater than 120dB (Linear) Peak at any time 5mm/second peak particle velocity for 9 out of 10 No blasting consecutive blasts and not greater than 10 mm/second peak particle velocity at any time C3 When requested by the administering authority, noise monitoring and recording must include the following descriptor characteristics and matters: a) LAN,T (where N equals the statistical levels of 1, 10 and 90 and T = 15 mins); b) Background noise LA90; c) The level and frequency of occurrence of impulsive or tonal noise and any adjustment and penalties to statistical levels; d) Atmospheric conditions including temperature, relative humidity and wind speed and directions; e) Effects due to any extraneous factors such as traffic noise; f) Location, date and time of monitoring; g) If the complaint concerns low frequency noise, Max Lp(lin)T and one third octave band measurements in dB(lin) for centre frequencies in the 10-200 Hertz range. END OF CONDITIONS FOR SCHEDULE C

    Noise and vibration, Monitoring and reporting
  15. Page 15

    OFFICIAL Permit Environmental authority EPML00658113 Schedule D - Water D1 Contaminants that will, or have the potential to cause environmental harm must not be released directly or indirectly to any waters as a result of the authorised mining activities, except as permitted under the conditions of this environmental authority. D2 The release of contaminants to waters must only occur from the release points specified in Table D1 - Contaminated water release points, sources and receiving waters. Table D1- Contaminated water release points, sources and receiving waters Release Location (GDA94) Water source[1] Receiving waters point[1] description Latitude Longitude (RP) East End Creek A -23.878593 150.967531 East End mining operations discharging East End Creek at Weir 1. 1 -23.878231 150.963540 East End mining operations discharging at Weir 6. [1] Locations depicted in Figure 2 - Release point and surface water monitoring locations. D3 The release of contaminants to waters in accordance with condition D2 must be monitored: a) at the release points specified in Table D1 - Contaminated water release points, sources and receiving waters as depicted in Figure 2 - Release points and surface water monitoring locations; and b) at the monitoring frequencies specified in Table D2 - Contaminant release limits; and c) for the quality characteristics identified in Table D2 - Contaminant release limits. D4 The release of contaminants to waters in accordance with condition D2 must not exceed the release limits stated in Table D2 - Contaminant release limits when measured at the release points specified in Table D1 - Contaminated water release points, sources and receiving waters for each quality characteristic. Table D2 - Contaminant release limits Quality characteristic Release limit [2] Monitoring frequency Electrical Conductivity 5,000 Daily during a release greater than 6 mega litres (micro siemens per per day. centimetre, -s/cm) Monthly for all other releases. pH (pH units) 6.5 (minimum) Turbidity (NTU) 8.5 (maximum) 20[1] [1] If turbidity at [the upstream monitoring point (Monitoring Point C)] is greater than Release Point A then no exceedance is to be recorded. [2] Release limits apply at Release Point 1 from 02 September 2022. D5 The release of contaminants to waters in accordance with condition D2 must only take place during periods of natural flow in the Larcom Creek. D6 Releases to waters must be undertaken so as to not cause erosion of the bed and banks of the receiving waters, or cause a material build-up of sediment in such waters.

    Surface water, Land and soil, Monitoring and reporting
  16. Page 16

    OFFICIAL Permit Environmental authority EPML00658113 D7 The rate and daily quantity of water released from the release points specified in Table D1 - Contaminated water release points, sources and receiving waters must be measured and recorded. D8 The environmental authority holder must determine and record stream flows in the receiving environment at the upstream reference monitoring point specified in Table D3 - Receiving waters monitoring sites. D9 If the release limits specified in Table D2 - Contaminant Release limits are exceeded, the holder of the environmental authority must notify the administering authority within twenty four (24) hours of receiving the results. D10 The environmental authority holder must, within twenty eight (28) days of a release that is not compliant with the conditions of this environmental authority, provide a report to the administering authority detailing: a) the reason for the release; and b) the location of the release; and c) the total volume of the release and which (if any) part of this volume was non-compliant; and d) the total duration of the release and which (if any) part of this period was non-compliant; and e) all water quality monitoring results (including all laboratory analyses); and f) identification of any environmental harm as a result of the non-compliance; and g) all calculations; and h) any other matters pertinent to the water release event. D11 The quality of the receiving waters must be monitored at the locations and frequency specified in Table D3 - Receiving waters monitoring sites as depicted in Figure 2 - Release points and surface water monitoring locations for each quality characteristic stated in Table D4 - Water quality objectives for receiving waters.

    Surface water, Monitoring and reporting
  17. Page 17

    OFFICIAL Permit Environmental authority EPML00658113 Table D3 - Receiving waters monitoring sites Monitoring point[1] Receiving waters location Location (GDA94) Monitoring frequency Latitude Longitude description Upstream reference monitoring point[1] Monitoring Point G Larcom Creek upstream of East TBD TBD Weekly -23.887238 150.977206 Weekly End Creek and Larcom Creek junction [2] Monitoring Point C Larcom Creek upstream of East End Creek and Larcom Creek junction (Location 5) Downstream monitoring points Monitoring Point D Larcom Creek downstream of -23.899252 150.976561 Weekly East End Creek and Larcom Creek Junction (at Weir 7) [1] Locations depicted in Figure 2 - Release point and surface water monitoring locations. [2] Upstream location must be outside of any influence from the releases from RP A TBD To be determined and provided to the administering authority by 02 December 2021. D12 Receiving waters measured from Monitoring Point D specified in Table D3 - Receiving waters monitoring sites must not exceed the corresponding Limit A specified in Table D4 - Water quality objectives for receiving waters on any five consecutive sampling occasions. D13 Receiving waters measured from Monitoring Point D specified in Table D3 - Receiving waters monitoring sites must not exceed the corresponding Limit B specified in Table D4 - Water quality objectives for receiving waters on any three consecutive sampling occasions. Table D4 - Water quality objectives for receiving waters Quality characteristic Water quality limit A Water quality limit B pH (pH units) NA 6.5 (minimum) [1] NA 8.0 (maximum)[1] Electrical conductivity 2,900[2] 3,300 [3] (micro siemens per centimetre, -S/cm) 4.2[1] 28.6 [5] Turbidity (NTU) [4] [1] Local water guideline values for protection of aquatic ecosystems for lowland fresh waters as per Table 2F of Environmental Protection (Water) Policy 2009 Curtis Island, Calliope River and Boyne River Basins Environmental Values and Water Quality Objectives), published in November 2014.. [2] Limit based on 75th percentile of Monitoring Point D specific data from January 2011 to March 2018. [3] Limit based on 95th percentile of Monitoring Point D specific data from January 2011 to March 2018. [4] If turbidity at Monitoring Point C is greater than Monitoring Point D then no exceedance is to be recorded. [5] Limit based on 95th percentile of Monitoring Point C specific data from January 2011 to April 2017.

    Surface water, Monitoring and reporting
  18. Page 18

    OFFICIAL Permit Environmental authority EPML00658113 D14 By 02 December 2021, the environmental authority holder must develop and implement a Receiving Environment Monitoring Program (REMP) in accordance with the Receiving Environment Monitoring program guideline for use with environmentally relevant activities under the Environmental Protection environmental values, quality and flows; and groundwater due to the mining activity. This must include monitoring the effects of the mine on the receiving environment periodically and while contaminants are being discharged from the site. For the purposes of the REMP, the receiving environment includes the waters of: - Larcom Creek; - East End Creek; - Machine Creek; - Jacobs Creek; - Scrub Creek; - Shultz Lagoon; and - Groundwater. D15 A report outlining the findings of the REMP, including all monitoring results and interpretations must be prepared biennially and submitted to the administering authority on request. This must include as a minimum an assessment of background reference water quality, the condition of downstream water quality compared against water quality objectives, the suitability of current discharge limits to protect downstream environmental values; and changes in groundwater quality. D16 A Water Management Plan must be developed by an appropriately qualified person and implemented by the environmental authority holder. D17 An Erosion and Sediment Control Plan (ESCP) must be developed by an appropriately qualified person and implemented by the environmental authority holder to minimise erosion and the release of sediment to receiving waters and contamination of stormwater. D18 The extraction of groundwater must not cause environmental harm to the terrestrial groundwater dependant ecosystems specified in Table D5 - Identified Terrestrial Groundwater Dependant Ecosystems or any groundwater dependant ecosystems outside of the zone of influence as depicted in Figure 4: Groundwater Zone of Influence. Table D5 - Identified Terrestrial Groundwater Dependant Ecosystems GDE Latitude Longitude 150.96963 Terrestrial GDE[1] -23.85373 [1] http://www.bom.gov.au/water/groundwater/gde/map.shtml D19 By 02 December 2021, a Groundwater Monitoring and Management Program must be developed, documented and implemented by an appropriately qualified person.

    Groundwater, Surface water, Land and soil, Monitoring and reporting
  19. Page 19

    OFFICIAL Permit Environmental authority EPML00658113 D20 The Groundwater Monitoring and Management Program required by condition D19 must: a) identify potential sources of contamination to groundwater from the activity; and b) ensure that all potential groundwater impacts due to the activity are identified, monitored and mitigated; and c) document sampling and monitoring methodology; and d) ensure that adequate groundwater monitoring and data analysis is undertaken to achieve the following objectives: i. detect any impacts to groundwater levels due to the activity; and ii. detect any impacts to groundwater quality due to the activity; and iii. determine compliance with condition D18; and iv. determine trends in groundwater quality; and e) include an appropriate quality assurance and quality control program; and f) include validation of the calibrated transient groundwater model; and g) include a review process to identify improvements to the program that includes addressing any comments provided by the administering authority. D21 The Groundwater Monitoring and Management Program required by condition D19 must be reviewed by 30 June each year by an appropriately qualified person to determine if it continues to meet the requirements stated in condition D20. D22 Groundwater quality and standing water level must be monitored: a) at the monitoring points specified in Table D6 - Groundwater monitoring locations and frequency; and b) at the monitoring frequencies specified in Table D6 - Groundwater monitoring locations and frequency; and c) for the quality characteristics identified in Table D7 - Groundwater quality limits for the aquifer in which the bore is located

    Groundwater, Monitoring and reporting
  20. Page 20

    OFFICIAL Permit Environmental authority EPML00658113 Table D6 - Groundwater monitoring locations and frequency Location (GDA94) Screened Monitoring Frequency Latitude Longitude interval RL Monitoring Point[1] Surface Standing Groundwater RL (m)[2] (m) Water Quality Level Limestone monitoring bores - Groundwater Quality within zone of influence DHH96-29 -23.872779 150.974047 36 20-36 DHH96-30 -23.874528 150.971084 20 15-27 DHH96-7 -23.900377 150.965663 50 8-50 Quarterly DHH96-20 -23.868636 150.953004 45 33-45 DHH96-25 -23.871112 150.969518 41.3 28-41.3 Volcaniclastic monitoring bores - Groundwater Quality within zone of influence DHH96-39 -23.888283 150.959185 TBA TBA Quarterly DHH96-14 -23.879067 150.941706 50 20-50 Subterranean Fauna Monitoring Bores DHH96-41 -23.891462 150.972234 36.67 TBA DHH96-33 TBA TBA TBA TBA EE Mine Forest Bore -23.874363 150.967503 TBA TBA SE DHH96-30 -23.874528 150.971084 20 15-27 Quarterly DHH96-29 -23.872779 150.974047 36 20-36 DHH96-7 -23.900377 150.965663 50 8-50 DHH97-6 -23.884431 150.969634 TBA TBA B100 -23.847465 150.951668 54.8 TBA Drawdown/GDE Monitoring Bores Limestone Compliance bores - Groundwater Levels and Quality DHH96-5 -23.852414 150.981157 44.77 10-50 Quarterly RC11-09 -23.798363 150.906876 30.487 24-36 Quarterly. Shultz lagoon 1 TBA TBA TBA TBA Shultz lagoon 2 TBA TBA TBA TBA Shultz lagoon 3 TBA TBA TBA TBA Volcaniclastic Compliance bores - Groundwater Levels and Quality DHH96-1 [3] -23.858826 150.974402 51.65 30-50 DHH96-2 [3] -23.855962 150.969479 51.85 0-20 DHH96-10 -23.87511 150.992037 41.51 27-50 DHH97-1A -23.858226 150.924669 67.662 10.3-19 Quarterly RC11-07 -23.832943 150.895126 71.183 30-100 RC11-13 -23.918103 150.996597 33.417 12-31 RC11-15 -23.896588 151.010276 44.975 18-76 RC11-17 -23.819972 150.96685 70.27 50-60

    Groundwater, Biodiversity, Monitoring and reporting
  21. Page 21

    OFFICIAL Permit Environmental authority EPML00658113 Location (GDA94) Screened Monitoring Frequency Latitude Longitude interval RL Monitoring Point[1] Surface Standing Groundwater RL (m)[2] (m) Water Quality Level RC11-19 -23.88478 150.931748 63.13 70-100 RC11-20 -23.901544 150.936513 62.887 16-32 RC11-21 -23.925181 150.924282 62.596 14-32 Southern New Bore 1 TBA TBA TBA TBA Quarterly. Southern New Bore 2 TBA TBA TBA TBA [1] Locations depicted in Figure 3 -Groundwater monitoring locations. [2] RL must be measured to the nearest 5cm from the top of the bore casing. [3] Terrestrial GDE specific monitoring bore TBA To be advised to the administering authority by 02 March 2022. D23 The activity must not cause a deterioration of groundwater quality. D24 Groundwater measured from any compliance bore specified in Table D6 - Groundwater monitoring locations and frequency must not exceed the corresponding Limit A specified in Table D7 - Groundwater quality limits on any five consecutive sampling occasions. D25 Groundwater measured from any compliance bore specified in Table D6 - Groundwater monitoring locations and frequency must not exceed the corresponding Limit B specified in Table D7 - Groundwater quality limits on any three consecutive sampling occasions. D26 If groundwater measured from any compliance bore specified in Table D6 - Groundwater monitoring locations and frequency exceeds the corresponding Limit B specified in Table D7 - Groundwater quality limits on any one sampling occasion the environmental authority holder must resample the groundwater within the compliance bore for all exceeding parameters within ten business days of receipt of results.

    Groundwater, Monitoring and reporting
  22. Page 22

    OFFICIAL Permit Environmental authority EPML00658113 Table D7 - Groundwater quality limits Quality Characteristic Monitoring Point pH (pH units) Electrical Conductivity (micro siemens Major ions[1] per centimetre (-s/cm)) (milligrams per DHH96-5 RC11-09 Range Maximum Maximum litre (mg/L)) Shultz lagoon 1 Limit A[2] Limit B[3] Shultz lagoon 2 21,912 24,151 NA Shultz lagoon 3 DHH96-1 [3] 5,830 5,920 TBA TBA TBA TBA TBA TBA 26,800 33,683 DHH96-2 [3] 9,880 13,413 DHH96-10 4,784 4,817 DHH97-1A 6.5 (minimum) 284 311 For interpretation RC11-07 8.0 (maximum) 5,840 6,740 purposes only. RC11-13 11,394 11,406 RC11-15 9,090 9,997 RC11-17 10,000 11,117 RC11-19 3,970 4,120 RC11-20 3,630 4,372 RC11-21 1,660 1,787 Southern New Bore 1 TBA TBA Southern New Bore 2 TBA TBA [1] Major ions include calcium, magnesium, sodium, potassium, bicarbonate, chloride, and sulphate. [2] Limit A has been determined from the 80th percentile of the specific bore historical groundwater quality data up to March 2017. [3] Limit B has been determined from the 95th percentile of the specific bore historical groundwater quality data up to March 2017. TBA To be advised to the administering authority by 02 November 2023.

    Groundwater, Monitoring and reporting
  23. Page 23

    OFFICIAL Permit Environmental authority EPML00658113 D27 If the standing water level of groundwater measured at any compliance bore specified in Table D6 - Groundwater monitoring locations and frequency is less than any of the corresponding trigger levels specified in Table D8 - Groundwater monitoring trigger levels, the environmental authority holder must: a) notify the administering authority within 24 hours; and b) conduct an investigation into the cause within ten business days; and c) if the mining activities are identified as a potential cause or contributor, take immediate action to ensure compliance with condition D18 of this environmental authority. Table D8 - Drawdown/GDE Groundwater monitoring trigger levels Monitoring Unit Trigger Levels [1] Limit Type Point Minimum Limestone Compliance bores - Groundwater Levels Minimum DHH96-5 38.2 RC11-09 24.6 Shultz lagoon 1 SWL m RL TBA Shultz lagoon 2 TBA Shultz lagoon 3 TBA Volcaniclastic Compliance bores - Groundwater Levels DHH96-1 [2] 44.1 DHH96-2 [2] 44.8 DHH96-10 34.5 DHH97-1A 60.4 RC11-07 55.3 RC11-13 24.2 RC11-15 SWL m RL 43.6 RC11-17 49.8 RC11-19 56.0 RC11-20 48.7 RC11-21 52.7 Southern New Bore 1 TBA Southern New Bore 2 TBA [1] 5th percentile minus 0.5 metre [2] Terrestrial GDE specific monitoring bores TBA To be advised to the administering authority by 02 November 2023.

    Groundwater, Monitoring and reporting
  24. Page 24

    OFFICIAL Permit Environmental authority EPML00658113 D28 Groundwater monitoring bores must be : a) constructed and maintained in a manner that ensures the integrity of the bores to obtain representative groundwater samples from the target aquifer; and b) constructed, maintained and decommissioned in a manner that: i. prevents contaminants entering the groundwater; and ii. that maintains the hydogeological environment within the aquifer. D29 A bore drill log must be kept for each groundwater monitoring bore which includes: a) bore identification reference and geographic coordinate location; b) specific construction information including but not limited to depth of bore, depth and length of casing, depth and length of screening and bore sealing details; c) standing groundwater level and water quality parameters including physical parameters and results of laboratory analysis for the possible trigger parameters; d) lithological data and stratigraphic interpretation by an appropriately qualified person to identify important features associated with groundwater monitoring; and e) target aquifer formation of the bore. D30 Monitoring and sampling must be carried out in accordance with written procedures and must address the requirements of the latest version of the following documents unless otherwise approved by the administering authority: a) for waters and aquatic environments, the Queensland Government's Monitoring and Sampling Manual 2009 - Environmental Protection (Water) Policy 2009 b) for groundwater, Groundwater Sampling and Analysis - A Field Guide (2009:27 GeoCat#6890.1) and Australian Standard AS/NZS 5667.11:1998 Water Quality - Sampling - Guidance on sampling of groundwaters; c) for subterranean aquatic fauna, the Guideline for the Environmental Assessment of Subterranean Aquatic Fauna. D31 Prior to the commencement of pit development on ML80156, a Subterranean Fauna Monitoring and Management Program must be developed by an appropriately qualified person and implemented by the environmental authority holder. D32 The Subterranean Fauna Monitoring and Management Program required by condition D31 must include adequate monitoring of subterranean species of stygofauna and troglofauna in all groundwaters potentially impacted by the mining activities and must achieve the following objectives: a) Identify and describe subterranean fauna species present; b) In addition to condition D32(a), accurately describe and determine the distribution of the unique taxa found at bore locations EEUN2 and DHH96-41; c) Assess and describe predicted impacts to subterranean fauna identified; d) Recommend impact mitigation and minimisation measures for the fauna identified; e) Monitor and record the effects of the mining activity on the subterranean fauna species; f) Recommend actions, including timeframes for implementation, to ensure that any impacts to subterranean fauna not authorised under this environmental authority, are prevented.

    Groundwater, Biodiversity, Monitoring and reporting
  25. Page 25

    OFFICIAL Permit Environmental authority EPML00658113 D33 If the standing water level of groundwater measured at any compliance bore specified in Table D6 - Groundwater monitoring locations and frequency is less than any of the corresponding trigger levels specified in Table D9 - Subterranean fauna trigger levels, the environmental authority holder must: a) notify the administering authority within 24 hours; and b) review the Subterranean Fauna Monitoring and Management Program required by condition D31 within ten business days, particularly the requirements of condition D32 c), d), e), and f). Table D9 - Subterranean fauna trigger levels Monitoring Unit Trigger Levels [1] Limit Type Point DHH96-30 SWL m RL 24.1 Minimum DHH97-6 25.1 EE Mine Forest Bore SE 20.4 DHH96-29 31.2 DHH96-41 29.9 DHH96-7 32.7 DHH96-33 TBA DHH96-39 42.7 B100 28.7 [1] 5th percentile minus 0.5 metre END OF CONDITIONS FOR SCHEDULE D

    Groundwater, Biodiversity, Monitoring and reporting
  26. Page 26

    OFFICIAL Permit Environmental authority EPML00658113 Schedule E - Land E1 Treated sewage effluent may only be released to land in accordance with the conditions of this environmental authority at the following locations: a) Within the nominated area(s) identified in Figure 5: Location of sewage effluent disposal area; and b) Other land for the purpose of dust suppression and/or firefighting. E2 The release of treated sewage effluent to land must not exceed the release limits stated in Table E1 - Contaminant release limits to land. Table E1 - Contaminant release limits to land Quality Characteristic Unit Release Limit type Monitoring limit frequency Five-day biochemical oxygen demand mg/L 20 Maximum Monthly (BOD) Total suspended solids mg/L 30 Maximum Nitrogen mg/L 30 Maximum Phosphorus mg/L 15 Maximum E-coli organisms/100mL 1000 Maximum pH pH units 6.5 - 9.0 Range E3 The application of treated effluent to land must be carried out in a manner that: a) Vegetation is not damaged; and b) There is no surface ponding of effluent; and c) There is no run-off of effluent. E4 If areas irrigated with effluent are accessible to employees or the general public, prominent signage must be provided advising that effluent is present and care should be taken to avoid consuming or otherwise coming into unprotected contact with the effluent. E5 All sewage effluent released to land must be monitored at the monitoring frequency and for the quality characteristics specified in Table E1 - Contaminant release limits to land. E6 The monthly volume of effluent released to land must be measured and recorded. E7 When circumstances prevent the irrigation or beneficial reuse of treated effluent such as during or following rain events, waters must be directed to a wet weather storage or alternative measures must be taken to store/lawfully dispose of effluent. E8 A minimum area of 10m2 of land, excluding any necessary buffer zones, must be utilised for the irrigation and/or beneficial reuse of treated sewage effluent. E9 The release of contaminated water to land, other than treated sewage effluent in accordance with the conditions of this environmental authority, must only occur from the release points specified in Table E2 - Contaminant release to land locations.

    Surface water, Air, Biodiversity, Monitoring and reporting
  27. Page 27

    OFFICIAL Permit Environmental authority EPML00658113 Table E2 - Contaminant release to land locations Release Location (GDA94) Contaminated water source[1] point[1] Latitude Longitude (RP) E -23.879990 150.949572 East End mining operations, including clay dumps and haul roads, discharging at the spillway from the western sediment pond E. F -23.886765 150.966112 East End mining operations, including clay dumps and haul roads, discharging at the spillway from southern sediment pond F. [1] Locations depicted in Figure 2 - Release point and surface water monitoring locations. E10 The release of contaminants to lands in accordance with condition E9 must not exceed the release limits for each quality characteristic stated in Table E3 - Contaminant release to land limits when measured at the release points specified in Table E2 - Contaminant release to land locations. Table E3 - Contaminant release to land limits Quality characteristic Release limit Monitoring frequency 5,000 Electrical Conductivity (EC) During a release (sample must be taken within (micro Siemens per 6.5 (minimum) 24 hours of commencement of release but before centimetre, -s/cm) 8.5 (maximum) cessation of the release). pH (pH units) E11 The release of contaminants to land in accordance with condition E9 must be monitored at the release points specified in Table E2 - Contaminant release to land locations and depicted in Figure 2 - Release points and surface water monitoring locations, for each quality characteristic and at the monitoring frequency specified in Table E3 - Contaminant release to land limits. E12 The release of contaminants to land in accordance with condition E9 must be carried out in a manner that: a) Drainage to groundwater and subsurface flows of contaminants to surface waters are prevented; and b) Surface pondage and run-off of contaminants is prevented; and c) Degradation of soil structure is minimised; and d) Soil sodicity and the build-up of heavy metals and metalloids in the soil and subsoil is minimised. E13 Land disturbed by mining activities must be rehabilitated in accordance with Table E4 - Rehabilitation requirements.

    Rehabilitation, Groundwater, Surface water, Regulated structures, Land and soil, Monitoring and reporting
  28. Page 28

    OFFICIAL Permit Environmental authority EPML00658113 Table E4 - Rehabilitation requirements Mine Rehabilitation Rehabilitation Indicators Completion criteria domain goal objectives Mine pit Safety assessment Validation in rehabilitation report that slopes slopes that Safe to Site is safe for of slopes that are are safe and predictions about future safety are greater humans humans and greater than 30- than 30- and wildlife animals now and and greater than Validation in water quality report that and in the foreseeable 5m in height surface and groundwater objectives are greater future met. than 5m End of pipe and in height Non-polluting Surface and receiving Evidence in Final Rehabilitation Report Mine water groundwater that waters meet that appropriate risk assessment has been storages Stable leave the lease will environmental undertaken and control measures are in Able to sustain aim to meet or authority place. Mine an agreed improve the water conditions. Final Rehabilitation Report will be prepared workings, post-mining quality objectives of as per administering authority rehabilitation void, water land use the receiving Geotechnical guidelines including: storages waters. Current studies of - The results of a site investigation Mine and future water workings, high - The results of a residual risk workings quality parameters walls and voids above will be maintained - Tree density assessment (including estimation of RL40 at levels that are monitoring and maintenance costs) acceptable for uses (trees/ha) - The results of contamination assessment, Active spoil downstream of the - Shrub density as required. dumps site. - Written statements from (shrubs/ha) landowners/landholders documenting any Low probability - Sedge/forb/grass agreement for transfer of management of rock falls with and maintenance commitments or transfer serious density of infrastructure ownership. consequences (grasses/ha) - A site management plan as required. - Species - An accompanying audit statement Mining and composition detailing the extent of rehabilitation, the rehabilitation will - Species diversity extent of ongoing management, aim to create a - Unvegetated maintenance or monitoring issues and landform with land area (%) the adequacy of the calculated financial use capability - Leaf litter depth assurance. and/or suitably and coverage similar to that prior - Erosion to disturbance, indicators unless other (e.g. depth beneficial land uses and spacing are pre-determined of erosion rills) and agreed. - Photographic records of the Mine wastes and site disturbed land will be rehabilitated to a condition that is self-sustaining or where the maintenance requirements are consistent with an agreed post-mining land use.

    Rehabilitation, Groundwater, Waste, Land and soil, Monitoring and reporting
  29. Page 29

    OFFICIAL Permit Environmental authority EPML00658113 E14 Rehabilitation must commence progressively in accordance with the plan of operations. E15 The environmental authority holder must minimise the potential for contamination of land by hazardous contaminants. END OF CONDITIONS FOR SCHEDULE E

    Rehabilitation, Waste
  30. Page 30

    OFFICIAL Permit Environmental authority EPML00658113 Definitions Key terms and/or phrases used in this document are defined in this section. Where a term is not defined, the definition in the Environmental Protection Act 1994, its regulations or environmental protection policies must be used. If a word remains undefined it has its ordinary meaning. Airblast overpressure energy transmitted from the blast site within the atmosphere in the form of pressure waves. The maximum excess pressure in this wave, above ambient pressure is the peak Airblast overpressure measured in decibels linear (dBL). Annual exceedance probability or AEP the probability that at least one event in excess of a particular magnitude will occur in any given year. Annual inspection report means an assessment prepared by a suitably qualified and experienced person containing details of the assessment against the most recent consequence assessment report and design plan (or system design plan): a) against recommendations contained in previous annual inspections reports b) against recognised dam safety deficiency indicators c) for changes in circumstances potentially leading to a change in consequence category d) for conformance with the conditions of this authority e) for conformance with the `as constructed' drawings f) for the adequacy of the available storage in each regulated dam, based on an actual observation or observations taken after 31 May each year but prior to 1 November of that year, of accumulated sediment, state of the containment barrier and the level of liquids in the dam (or network of linked containment systems) g) for evidence of conformance with the current operational plan. Appropriately qualified person a person who has professional qualifications, training, skills or experience relevant to the nominated subject matter and can give authoritative assessment, advice and analysis on performance relating to the subject matter using the relevant protocols, standards, methods or literature. Assessed and assessment by a suitably qualified and experienced person in relation to a consequence assessment of a dam, means that a statutory declaration has been made by that person and, when taken together with any attached or appended documents referenced in that declaration, all of the following aspects are addressed and are sufficient to allow an independent audit of the assessment: a) exactly what has been assessed and the precise nature of that determination; b) the relevant legislative, regulatory and technical criteria on which the assessment has been based; c) the relevant data and facts on which the assessment has been based, the source of that material, and the efforts made to obtain all relevant data and facts; and d) the reasoning on which the assessment has been based using the relevant data and facts, and the relevant criteria. Associated works in relation to a dam means: a) operations of any kind and all things constructed, erected or installed for that dam; and b) any land used for those operations

    Regulated structures, Noise and vibration, Land and soil, Monitoring and reporting
  31. Page 31

    OFFICIAL Permit Environmental authority EPML00658113 Background with reference to the water schedule means the average of samples taken prior to the commencement of mining from the same waterway that the current sample has been taken. Blasting the use of explosive materials to fracture: a) rock, coal and other minerals for later recovery; or b) structural components or other items to facilitate removal from a site or for reuse. Certification means assessment and approval must be undertaken by a suitably qualified and experienced person in relation to any assessment or documentation required by a condition of this environmental authority, and specifically in relation to structures, means the Manual for Assessing Consequence Categories specifications, construction, operation or an annual report regarding regulated structures, undertaken in accordance with the Board of Professional Engineers of Queensland Policy Certification by RPEQs (ID: 1.4 (2A)). Certification, certifying or certified have a corresponding meaning as `certification'. Consequence in relation to a structure as defined, means the potential for environmental harm resulting from the collapse or failure of the structure to perform its primary purpose of containing, diverting or controlling flowable substances. Consequence category means a category, either low, significant or high, into which a dam is assessed as a result of the application of tables and other criteria in the Manual for Assessing Consequence Categories and Construction or constructed in relation to a dam includes building a new dam and modifying or lifting an existing dam, but does not include investigations and testing necessary for the purpose of preparing a design plan. Dam a land-based structure or a void that contains, diverts or controls flowable substances, and includes any substances that are thereby contained, diverted or controlled by that land-based structure or void and associated works. Dam crest volume means the volume of material (liquids and/or solids) that could be within the walls of a dam at any time when the upper level of that material is at the crest level of that dam. That is, the instantaneous maximum volume within the walls, without regard to flows entering or leaving (e.g. via spillway). Design plan is a document setting out how all identified consequence scenarios are addressed in the planned design and operation of a regulated structure. Design storage allowance or DSA means an available volume, estimated in accordance with the Manual for the administering authority, must be provided in a dam as at 1 November each year in order to prevent a discharge from that dam to an annual exceedence probability (AEP) specified in that Manual. Designer for the purposes of a regulated dam, means the certifier of the design plan for the regulated dam. Deterioration of groundwater quality means a material increase (or decrease for pH) to the concentration of a contaminant identified in groundwater monitoring data. Disturbance of land includes:

    Groundwater, Regulated structures, Noise and vibration, Monitoring and reporting
  32. Page 32

    OFFICIAL Permit Environmental authority EPML00658113 a) compacting, removing, covering, exposing or stockpiling of earth b) removal or destruction of vegetation or topsoil or both to an extent where the land has been made susceptible to erosion; c) carrying out mining within a watercourse, waterway, wetland or lake; d) the submersion of areas by tailings or hazardous contaminant storage and dam/structure walls; e) temporary infrastructure, including any infrastructure (roads, tracks, bridges, culverts, dam/structures, bores, buildings, fixed machinery, hardstand areas, airstrips, helipads etc.) which is to be removed after the mining activity has ceased; or f) releasing of contaminants into the soil, or underlying geological strata. Effluent treated waste water released from sewage treatment plants. Emergency action plan means documentation forming part of the operational plan held by the environmental authority holder or a nominated responsible officer, that identifies emergency conditions that sets out procedures and actions that will be followed and taken by the dam owner and operating personnel in the event of an emergency. The actions are to minimise the risk and consequences of failure, and ensure timely warning to downstream communities and the implementation of protection measures. The plan must require dam owners to annually update contact details. Existing structure means a structure that prior to 02 September 2021 meets any or both of the following, a structure: Assessing Consequence Categories and Hydraulic Performance of Structures b) That is under considerable construction or that is constructed. Flowable substance means matter or a mixture of materials which can flow under any conditions potentially affecting that substance. Constituents of a flowable substance can include water, other liquids fluids or solids, or a mixture that includes water and any other liquids fluids or solids either in solution or suspension. Hydraulic performance means the capacity of a regulated dam to contain or safely pass flowable substances based on the design criteria specified for the relevant consequence category in the Manual for Assessing Infrastructure means water storage dams, levees, roads and tracks, buildings and other structures built for the purpose of the mining activity. Land in the `land schedule' of this document means land excluding waters and the atmosphere, that is, the term has a different meaning from the term as defined in the Environmental Protection Act 1994. For the purposes of the Acts Interpretation Act 1954, it is expressly noted that the term `land' in this environmental authority relates to physical land and not to interests in land. Land use the selected post mining use of the land, which is planned to occur after the cessation of mining operations. Levee means an embankment that only provides for the containment and diversion of stormwater or flood flows from a contributing catchment, or containment and diversion of flowable materials resulting from releases from other works, during the progress of those stormwater or flood flows or those releases; and does not store any significant volume of water or flowable substances at any other times.

    Groundwater, Surface water, Regulated structures, Waste, Land and soil, Biodiversity
  33. Page 33

    OFFICIAL Permit Environmental authority EPML00658113 Low consequence structure means any structure that is not a high or significant consequence category as assessed using the Manual for Assessing Consequence Categories and Hydraulic Performance of Dams Mandatory reporting level or MRL means a warning and reporting level determined in accordance with the criteria in the Manual for Assessing Consequence Categories and Hydraulic Performance of Dams Manual means the Manual for Assessing Consequence Categories and Hydraulic Performance of Structures Measures include any measures to prevent or minimise environmental impacts of the mining activity such as bunds, silt fences, diversion drains, capping and containment systems. Modification or modifying see definition of `construction'. Natural flow the flow of water through waters caused by nature. Non-polluting having no adverse impacts upon the receiving environment. Operational plan includes: a) normal operating procedures and rules (including clear documentation and definition of process inputs in the DSA allowance); b) contingency and emergency action plans including operating procedures designed to avoid and/or minimise environmental impacts including threats to human life resulting from any overtopping or loss of structural integrity of the regulated structure. Peak particle velocity (ppv) a measure of ground vibration magnitude which is the maximum rate of change of ground displacement with time, usually measured in millimetres/second (mm/s). Pit development means the act or process of making an excavation or cut of the ground for the purpose of extracting ore. Receiving environment in relation to an activity that causes or may cause environmental harm, means the part of the environment which the harm is, or may be caused. The receiving environment includes (but is not limited to): a) a watercourse; b) groundwater; and c) an area of land that is not specified in this environmental authority. Receiving waters means waters of the receiving environment as defined in the Environmental Protection Act 1994, including but not limited to the waters of East End Creek, Shultz Lagoon, Larcom Creek, Machine Creek, Scrub Creek and Jacobs Creek. Records include breach notifications, written procedures, analysis results, monitoring reports and monitoring programs required under a condition of this authority.

    Groundwater, Surface water, Regulated structures, Noise and vibration, Monitoring and reporting
  34. Page 34

    OFFICIAL Permit Environmental authority EPML00658113 Register of regulated structures includes: a) date of entry in the register; b) name of the structure, its purpose and intended/actual contents; c) the consequence category of the structure as assessed using the Manual for Assessing d) dates, names and reference for the design plan plus dates, names and reference numbers of all document/s lodged as part of a design plan for the structure; e) name and qualifications of the suitably qualified and experienced person who certified the design plan and `as constructed' drawings; f) for the regulated dam, other than in relation to any levees: i. the dimensions (metres) and surface area (hectares) of the dam measured at the footprint of the dam; ii. coordinates (latitude and longitude in GDA94) within five (5) metres at any point from the outside of the dam including its storage area; iii. dam crest volume (megalitres); iv. spillway crest level (metres AHD); v. maximum operating level (metres AHD); vi. storage rating table of stored volume versus level (metres AHD); vii. design storage allowance (megalitres) and associated level of the dam (metres AHD); viii. mandatory reporting level (metres AHD); g) For a regulated levee: i. The crest length of the levee (metres) measured along the centreline of the levee; ii. Location Coordinates (latitude and longitude in GDA94), and chainage distances (metres), of each end of the levee, and of each point along the crest of the levee which marks a change in direction; iii. Levee crest level (metres AHD), also at each end of the levee, and at each point along the crest of the levee which marks a change in direction; iv. Maximum height of the levee (metres), from the crest level to the adjacent toe (inside or outside) of the embankment, and the location and chainage of this maximum height; v. The crest width of the levee (metres); vi. The Annual Exceedence Probability of the design flood for operation of the levee; vii. The freeboard (metres) between design flood level and the crest level of the levee; h) the design plan title and reference relevant to the dam; i) the date construction was certified as compliant with the design plan; j) the name and details of the suitably qualified and experienced person who certified that the constructed structure was compliant with the design plan; k) details of the composition and construction of any liner; l) the system for the detection of any leakage through the floor and sides of the dam; m) dates when the regulated structure underwent an annual inspection for structural and operational adequacy, and to ascertain the available storage volume for 1 November for any year; n) dates when recommendations and actions arising from the annual inspection were provided to the administering authority; o) dam water quality as obtained from any monitoring required under this authority as at 1 November of each year. Regulated structure means any structure in the significant or high consequence category as assessed by using the Manual for Assessing Consequence Categories and Hydraulic Performance of Dams

    Regulated structures, Monitoring and reporting
  35. Page 35

    OFFICIAL Permit Environmental authority EPML00658113 or manufactured tank or container, designed and constructed to an Australian Standard that deals with strength and structural integrity of that tank or container. Rehabilitation means the process of reshaping and revegetating land to restore it to a stable landform. Release event means surface water discharge from water storages or contaminated areas on the mining tenements detailed in this environmental authority. Representative a sample set which covers the variance in monitoring or other data either due to natural changes or operational phases of the mining activities. RL reduced level, relative to mean sea level as distinct from depths to water. Sensitive receptor means a sensitive receptor under the Environmental Protection (Noise) Policy 2008. Structure means dam or levee. Spillway means a weir, channel, conduit, tunnel, gate or other structure designed to permit discharges from the dam, normally under flood conditions or in anticipation of flood conditions. Subterranean Fauna means fauna which live their entire lives (obligate) below the surface of the earth consisting of air-breathing troglofauna or aquatic groundwater fauna. Subterranean wetland for the purpose of this environmental authority, means aquifer and cave groundwater dependent ecosystems that are dependent on the subterranean presence of groundwater. Suitably qualified and experienced person in relation to regulated structures means a person who is a Registered Professional Engineer of Queensland (RPEQ) under the provisions of the Professional Engineers Act 2002, and has demonstrated competency and relevant experience: a) For regulated dams, an RPEQ who is a civil engineer with the required qualifications in dam safety and dam design; b) For regulated levees, an RPEQ who is a civil engineer with the required qualifications in the design of flood protection embankments. Note: It is permissible that a suitably qualified and experienced person obtain subsidiary certification from an RPEQ who has demonstrated competence and relevant experience in other geomechanics, hydraulic design or engineering hydrology. System design plan means a plan that manages an integrated containment system that shares the required DSA volume and/or Extreme Storm Surge volume across the integrated containment system. Calibrated transient groundwater model means a calibrated groundwater model as described in the Australian Groundwater Modelling Guidelines published in 2012 by the Australian Government National Water Commission. The model must include time-varying inputs, calculate and save output at various times throughout the duration of the model run, and must be capable of predicting time-varying groundwater responses. Valid complaint means all complaints unless considered by the administering authority to be frivolous, vexatious or based on mistaken belief. Void means any constructed, open excavation in the ground. Water quality means the chemical, physical and biological condition of water.

    Rehabilitation, Groundwater, Surface water, Regulated structures, Noise and vibration, Subsidence, Biodiversity, Monitoring and reporting
  36. Page 36

    OFFICIAL Permit Environmental authority EPML00658113 Waters includes all or any of a river, stream, lake, lagoon, pond, swamp, wetland, unconfined surface water, unconfined natural or artificial watercourse, bed and bank of a watercourse, dams, non-tidal or tidal waters (including the sea), stormwater channel, stormwater drain, roadside gutter and groundwater. Wetland for the purpose of this environmental authority, means: a) Areas shown on the Map of referable wetlands which is a document approved by the chief executive on 4 November 2011 and published by the administering authority, as amended from time to time by the chief executive under section 144D of the Environmental Protection Regulation 2008; and b) Areas defined under the Queensland Wetlands Program as permanent or periodic / intermittent inundation, with water that is static or flowing fresh, brackish or salt, including areas of marine water, the depth of which at low tide does not exceed six (6) metres, and possess one or more of the following attributes: i. At least periodically, the land supports plants or animals that are adapted to and dependent on living in wet conditions for at least part of their life cycle; or ii. The substratum is predominantly undrained soils that are saturated, flooded or ponded long enough to develop anaerobic conditions in the upper layers, or; iii. The substratum is not soil and is saturated with water, or covered by water at some time. The term wetland includes riverine, lacustrine, estuarine, marine and palustrine wetlands; and it does not include a Great Artesian Basin Spring or a subterranean wetland that is a cave or aquifer.

    Groundwater, Surface water, Regulated structures, Land and soil
  37. Page 37

    OFFICIAL Permit Environmental authority EPML00658113 Appendices Maps and Figures Figure 1 - Project Infrastructure Layout Mine Area and Support Infrastructure. (eDOCS#6433223) Permit

  38. Page 38

    OFFICIAL Environmental authority EPML00658113 Figure 2 - Release Points and Surface water monitoring locations.

    Surface water, Monitoring and reporting
  39. Page 39

    OFFICIAL Permit Environmental authority EPML00658113 Figure 3 - Groundwater monitoring locations (source: Groundwater modelling report: Conceptualisation and Modelling approach, dated 11 January 2018 - eDOCS#6428179)

    Groundwater, Monitoring and reporting
  40. Page 40

    OFFICIAL Permit Environmental authority EPML00658113 Figure 4 - Groundwater Zone of Influence. (Modelled `zone of influence' (5m Drawdown Curve 2045) - - Pit Extension - Scenario 3 - MLA80156). Source: Groundwater modelling report: Conceptualisation and Modelling approach. 11 January 2018 (eDOCS#6428179).

    Groundwater, Monitoring and reporting
  41. Page 41

    OFFICIAL Permit Environmental authority EPML00658113 Figure 5: Location of sewage effluent disposal area END OF ENVIRONMENTAL AUTHORITY