Mining Capital FundsMCF Mining Approvals Index

Data as at 12 November 2026 · from Western Australian Government registers and open data

Western Australian mining project · Care and Maintenance

Whim Creek - Mons Cupri

Whim Creek - Mons Cupri is a Western Australian mining project (in care and maintenance) in MINEDEX, owned by Anax Metals Limited 80%; Develop Global Limited 20%; Venturex Pilbara Pty Ltd; Mainland Minerals Pty Ltd; Whim Creek Metals Pty Ltd; Jetosea Pty Limited, on 7 current tenements held by MAINLAND MINERALS PTY LTD; VENTUREX PILBARA PTY LTD; WHIM CREEK METALS PTY LTD. Commodities: Copper, Zinc, Lead, Gold, Silver.

MINEDEX project
J00711
Stage
Care and Maintenance
Owners (MINEDEX)
Anax Metals Limited 80%; Develop Global Limited 20%; Venturex Pilbara Pty Ltd; Mainland Minerals Pty Ltd; Whim Creek Metals Pty Ltd; Jetosea Pty Limited
Tenement holders
MAINLAND MINERALS PTY LTD
VENTUREX PILBARA PTY LTD
WHIM CREEK METALS PTY LTD
Parent groups
Anax Metals
Commodities
Copper, Zinc, Lead, Gold, Silver
Rehabilitation liability
Its rehabilitation liability is in the MCF Mining Index (subscribers): the Mining Rehabilitation Fund estimate, its trend since 2014, company provisions and closure-plan costs

Resources and reserves

CommodityResourcesReservesLatest estimate
Zinc8.88 Mt at 0.94%, 84 kt contained3.27 Mt at 1.3%, 41 kt contained25 August 2026
Lead8.88 Mt at 0.36%, 32 kt contained3.27 Mt at 0.47%, 15 kt contained25 August 2026
Gold8.88 Mt at 0.12 g/t, 35 koz contained3.27 Mt at 0.17 g/t, 18 koz contained25 August 2026
Silver8.88 Mt at 18.12 g/t, 5.18 Moz contained3.27 Mt at 24.34 g/t, 2.56 Moz contained25 August 2026
Copper8.88 Mt at 0.83%, 73 kt contained3.27 Mt at 1.2%, 39 kt contained25 August 2026

Current MINEDEX estimates over all the project's sites; resources may include reserves. MINEDEX (DMPE), CC BY 4.0.

Production recorded in MINEDEX

CommodityLatest yearThat yearAll recorded
Copper——11 kt

Historical: the bulk extract's production records end in 2002.

Mine closure plans

SiteOperatorLatest plan approvedPlan (PDF on GeoDocs)Closure year
Whim Creek Copper Project - Mine Closure Plan - Version 2 (2016 Update) ID Number - VXR20161130DEVELOP GLOBAL Limited

Tenements

TenementHolderStatusExpiresCommoditiesHectares
M 47/236
Mining lease
VENTUREX PILBARA PTY LTD; WHIM CREEK METALS PTY LTDGranted26 July 2032Copper, Zinc, Lead, Gold, Silver962
M 47/237
Mining lease
VENTUREX PILBARA PTY LTD; WHIM CREEK METALS PTY LTDGranted26 July 2032Copper, Gold411
M 47/238
Mining lease
VENTUREX PILBARA PTY LTD; WHIM CREEK METALS PTY LTDGranted26 July 2032Copper, Zinc, Lead, Gold, Silver979
M 47/443
Mining lease
VENTUREX PILBARA PTY LTD; WHIM CREEK METALS PTY LTDGranted1 June 2040Copper, Gold, Zinc, Lead, Silver40
L 47/36
Miscellaneous licence
VENTUREX PILBARA PTY LTD; WHIM CREEK METALS PTY LTDGranted18 January 2028Copper7
E 47/3495
Exploration licence
VENTUREX PILBARA PTY LTD; WHIM CREEK METALS PTY LTDGranted31 July 2027Copper, Gold, Lead, Zinc, Silver4,723
E 47/5275
Exploration licence
MAINLAND MINERALS PTY LTDApplicationLead, Silver, Copper, Zinc, Gold20,756